Seven one bedroom modular homes on a former garage site at Gatehouse Road, Aylesbury, with bold coloured cladding.

Gatehouse Road, Aylesbury - Seven modular terraced homes
Scheme
Seven modular terraced homes
Type
New build
Site inspections
5
Services
2
Status
Complete 2025

About the project

This job replaced a block of garages in Aylesbury with seven one bedroom homes. They are self-contained, single storey modular houses set out in a terrace.

We provided building control and a 10 year structural warranty, following the homes from the first site visits in 2023 through to completion.

By September 2024 the units were in position with windows and doors fitted, plasterboard going in and moisture resistant board in the wet areas. By March 2025 they were 90% complete, with treble glazing, MVHR and kitchens fitted. All internal and external work, including the cladding, was finished by July 2025.

On site

The build, stage by stage

  1. Gatehouse Road, Aylesbury - Foundations

    Stage 1

    Foundations

    The old garages were cleared and foundations and service runs were set out across the site.

  2. Gatehouse Road, Aylesbury - Walls

    Sep 2024

    Walls

    The modular units were in position with windows and doors fitted and plasterboarding under way.

  3. Gatehouse Road, Aylesbury - Finishes

    Mar 2025

    Finishes

    The units reached 90% complete, with triple glazing, MVHR and kitchens fitted.

  4. Gatehouse Road, Aylesbury - Complete

    Jul 2025

    Complete

    All external and internal works were completed, including the external cladding.