The story of the job
Five three-bedroom detached bungalows on Seeds Lane in Brownhills. We brought in our supply chain partners to provide Building Control and the 10 Year Structural Warranty for the client.
Foundations started from December 2022, dug to the structural engineer's design at 0.6m wide and 1.0m to 1.3m deep in sand and gravel with small clay pockets. Block and beam floors followed by April 2023, with air bricks in position and a damp-proof course under the precast beams.
Blockwork and brickwork came next, and by May 2023 roof trusses were erected to the manufacturer's design with wind bracing completed and girder trusses fully fixed. Foundations on later plots were still going in that month, with structural mesh reinforcement, so the site ran at several stages at once.
First fix plumbing, electrics and studwork ran from June to September 2023, with cavity wall insulation going in during July. By the end of October 2023 the drain test had been witnessed and all internal and external works were complete, with fire doors and overhead closers fitted to the integral garages.