A two-storey rear extension with steel columns and beams carrying bi-fold doors, on Borough Way in Nuneaton.

Borough Way, Nuneaton - project photo 1
Scheme
Two-storey rear extension
Type
Extension
Site inspections
5
Services
2
Status
Complete 2023

About the project

This is a two-storey rear extension on Borough Way in Nuneaton. The design needed structural calculations to carry a run of bi-fold doors.

We provided Building Control together with the Structural Engineering design and calculations, so one team covered both the design and the checks on site.

Foundations went in during May 2023 at approximately 1.3m deep, followed by an insulated ground floor. By the end of June the 150mm cavity walls and the universal steel columns and beams were in, and the roof trusses followed by August.

On site

The build, stage by stage

  1. Borough Way, Nuneaton - Foundations

    May 2023

    Foundations

    Foundations were excavated to approximately 1.3m deep and 0.6m wide, with the existing foundation exposed.

  2. Borough Way, Nuneaton - Walls

    Jun 2023

    Walls

    Walls went up around a 150mm fully filled cavity, with universal steel columns and beams installed to the structural engineer's design.

  3. Borough Way, Nuneaton - Roof

    Aug 2023

    Roof

    Roof trusses went on with diagonal and longitudinal wind bracing.

Photos from site

Call usGet a free quote