About the project
This is a two-storey rear extension on Borough Way in Nuneaton. The design needed structural calculations to carry a run of bi-fold doors.
We provided Building Control together with the Structural Engineering design and calculations, so one team covered both the design and the checks on site.
Foundations went in during May 2023 at approximately 1.3m deep, followed by an insulated ground floor. By the end of June the 150mm cavity walls and the universal steel columns and beams were in, and the roof trusses followed by August.