This is a two-storey commercial and laboratory unit for a hazardous waste operation, with offices on the first floor.
We provided Building Control, checking compliance through construction, including structure, fire safety and ventilation.
Our first visit was in June 2023, when the pad foundations were inspected against the structural engineer's design in medium shrinkable clay. By October the steel frame was up on a blue brick substructure and the first floor decking was going in, across five inspection visits.