Hinckley Road

Stoney Stanton

A detached house, a bungalow and a two-storey rear extension built on Hinckley Road, Stoney Stanton.

Hinckley Road, Stoney Stanton - New house, bungalow and rear extension
Scheme
New house, bungalow and rear extension
Type
New build
Site inspections
9
Services
8
Status
In progress

The story of the job

This job on Hinckley Road in Stoney Stanton covers three pieces of work on one site: a two-storey three-bedroom detached house with an integral garage, a single-storey two-bedroom detached bungalow, and a two-storey rear extension to the existing house.

We coordinated Building Control and the 10 Year Structural Warranty, along with the Phase 1 Desk Study, SAP calculations, air tightness and ventilation testing, Energy Performance Certificates and water efficiency calculations.

Foundations on the first plot went down 1.0m into medium shrinkable clay at 0.6m wide, with water pumped out before the pour. Block and beam floors followed in May 2023, roof trusses by the end of that month and first fix by July. By November 2023 the driveway was laid and all internal and external works on that phase were complete.

The next phase picked up in January 2024 with a block and beam floor and first lift brickwork. Engineered joists were going in by February 2026. At the September 2026 visit roof tiling was complete with a mechanically fixed ventilated ridge, and steel beams and a wind post were bolted in place. This phase is still running.

01

The challenge

Three builds shared one site: a new house, a new bungalow and a two-storey extension to the existing house. The ground was medium shrinkable clay, and water had to be pumped out of the trenches before concrete went in. The work ran in phases from 2023 into 2026.

02

How we ran it

We made nine inspection visits, covering foundations, block and beam floors, roofs and first fix across the phases. Alongside them we coordinated SAP calculations, air tightness and ventilation testing, Energy Performance Certificates and water efficiency calculations.

03

The result

The first phase finished in November 2023 with all internal and external works complete and the driveway laid. The later phase is still running, and by September 2026 its roof tiling was complete with a mechanically fixed ventilated ridge.

On site

The build, stage by stage

  1. Hinckley Road, Stoney Stanton - Foundations

    Stage 1

    Foundations

    Foundations on the first plot were dug 1.0m deep and 0.6m wide into medium shrinkable clay.

  2. Hinckley Road, Stoney Stanton - Floors

    May 2023

    Floors

    The block and beam floor went in with air bricks fitted and a 250mm air void under the precast beams.

  3. Hinckley Road, Stoney Stanton - Roof

    May 2023

    Roof

    Roof trusses went up and were inspected on site.

  4. Hinckley Road, Stoney Stanton - First fix

    Jul 2023

    First fix

    First fix carpentry, plumbing and electrics were completed, with the ventilated ridge system in position.

  5. Hinckley Road, Stoney Stanton - Finishes

    Nov 2023

    Finishes

    All internal and external works were complete on the first phase, with the driveway laid and gutters connected.

  6. Hinckley Road, Stoney Stanton - Roof

    Sep 2026

    Roof

    On the later phase roof tiling was completed, with steel beams and a wind post bolted in place.

One point of contact

Where we fitted in

Before site

Design, calculations and surveys

  • Phase 1 Desk Study
  • SAP Calculations (New Build)
  • Water Efficiency Calculations

During the build

Approvals, cover and materials

  • Building Control
  • 10 Year Structural Warranty

At sign-off

Testing and certificates

  • Air Tightness Testing
  • Ventilation Testing
  • Energy Performance Certificates