About the project
This job was close to home for us: the demolition of an existing house on Higham Lane in Nuneaton and the construction of a new 2.5-storey, five-bedroom detached home.
We provided building control, with our local inspector seeing the project through from start to finish, and the 10-year structural warranty.
Foundations went in during March 2021 in medium shrinkable clay, stepping from 1.5m at one gable up to 1.0m, with the block and beam floor following the same month. The brickwork reached third lift by June, the cut roof was on by July, and our last visit was in April 2022.