Future Homes Standard starts 24 March 2027. Is your site caught? Check in 30 seconds →
Mon–Fri 9am–5pm02475 095700

Project

Hillside Drive

Nuneaton

A two-storey, three-bedroom detached house on Hillside Drive in Nuneaton.

Hillside Drive, Nuneaton - Three-bedroom detached house
Scheme
Three-bedroom detached house
Type
New build
Site inspections
6
Services
2
Status
Complete 2023

About the project

This was a single two-storey, three-bedroom detached house on Hillside Drive in Nuneaton. We provided the Structural Engineering and the 10 Year Structural Warranty.

Work started in May 2022 with foundations dug 1.0m deep and 0.6m wide in medium shrinkable clay. By June the substructure was up to damp proof course in blue bricks with the block and beam floor complete.

The walls reached the third lift in early July and the roof was on by the end of the month. First fix was finished by August 2022, and the last visit followed in January 2023.

On site

The build, stage by stage

  1. Hillside Drive, Nuneaton - Foundations

    May 2022

    Foundations

    Foundations were dug 1.0m deep and 0.6m wide in medium shrinkable clay.

  2. Hillside Drive, Nuneaton - Floors

    Jun 2022

    Floors

    Substructure brickwork and blockwork reached damp proof course level and the block and beam floor was completed.

  3. Hillside Drive, Nuneaton - Walls

    Jul 2022

    Walls

    External brickwork and internal blockwork reached the third lift, with insulation and lintels in.

  4. Hillside Drive, Nuneaton - Roof

    Jul 2022

    Roof

    The roof went on with wind bracing, truss clips and lateral restraint straps fixed.

  5. Hillside Drive, Nuneaton - First fix

    Aug 2022

    First fix

    First fix electrics and plumbing were completed and partition insulation went in.

  6. Hillside Drive, Nuneaton - Complete

    Jan 2023

    Complete

    Windows, extractor fans and smoke detectors were fitted by the last visit.

Photos from site

Call usGet a free quote