About the project
This was a nine-home development on the site of the former Jolly Colliers at Newhall in Swadlincote, built for a regular client. The scheme is six two storey, three bedroom semi-detached houses and three two storey, three and four bedroom detached houses.
We put together a wide package for the job: building control, a 10 year structural warranty and the Phase 1 desk study, along with SAP calculations, EPCs and water calculations. Air tightness, sound and ventilation testing followed, and we also supplied the floor joists and roof trusses and cavity wall insulation.
Work started on site in September 2022 with foundations in medium shrinkable clay, after the ground had been grouted. Floors followed before Christmas, walls and joists by February 2023 and the trusses soon after. Over 15 visits we followed the build through to final inspection in June 2023.