Underpinning Building Regulations
Underpinning means making a building’s foundations deeper or stronger, usually because the building has moved or because it is about to carry more weight. In England it always counts as building work, so it needs building regulations approval and a structural engineer’s design. This guide explains what the approval involves, how the work is normally done and inspected, and when the Party Wall Act comes into it.
The points below come from the Building Regulations 2010 on legislation.gov.uk, the Planning Portal’s underpinning pages and the government’s Party Wall etc. Act 1996 explanatory booklet on GOV.UK.
Do you need building regulations approval?
Yes. Regulation 3 of the Building Regulations 2010 lists what counts as building work, and “work involving the underpinning of a building” is named in that list. So underpinning all or part of a house, an extension or a garage needs approval in the same way as an extension does.
The Planning Portal adds that getting approval will usually mean preparing a structural design for the underpinning, including how it will be carried out on site. Building Control then checks the work at the key stages.
You can apply to the council’s building control team or to a registered building control approver. A full plans application lets Building Control check the engineer’s design before anyone starts digging, which is the safer route for work below an existing house.
Do you need planning permission?
Usually not. The Planning Portal says maintenance on foundations generally does not need planning permission. The exceptions to check first:
Listed buildings
Ask the council before any work. Listed building consent is separate from planning permission and from building regulations.
Designated areas
In a conservation area, national park or area of outstanding natural beauty, the Planning Portal advises checking with the council before work starts.
Extra storeys or a basement
If the underpinning is part of a bigger project, such as digging a basement or adding a storey, that project may need planning permission of its own.
Why a building gets underpinned
The Planning Portal gives two main reasons:
The foundations have moved
Poor ground, or a change in the ground such as subsidence, has made the existing foundations move.
The building is getting heavier or deeper
Another storey above ground, or a new level below it, means the existing foundations are not deep enough to carry the new load.
Underpinning only works if the cause of the movement is understood first. Before it is designed, an engineer will want to know why the building moved and whether it is still moving. Cracks on their own do not always mean underpinning is needed. If you think the cause is subsidence, tell your home insurer before you arrange any work, as they will usually want to send their own engineer.
What the engineer needs to design it
The Planning Portal says the first step, before the main work starts, will generally be a trial hole dug next to the existing footings. That lets a structural engineer or surveyor see how deep the foundations are, what they are made of and what the ground below is like.
Depending on what the trial hole shows, the engineer may ask for more ground information, such as further trial pits, boreholes or soil tests from a site investigation. Clay soils and nearby trees can affect how deep the new foundations need to go.
The design then sets out:
Depth and size
How deep the new foundation goes and how wide each section is.
Order of work
Which sections are dug first, how many can be open at once and how far apart they must be.
Materials
The concrete, any steel reinforcement and the packing used to close the gap under the old footing.
Drains and services
How nearby drains and pipes are protected. The Planning Portal says particular attention is needed for sewers and drains near the work.
How underpinning is done and inspected
The Planning Portal describes the usual method. The soil under the existing foundation is dug out and replaced with new foundation material, normally concrete, in short sections, one at a time. More than one section can sometimes be dug at once, but only when they are far enough apart. This stops too much of the old foundation being left unsupported, which could damage the building above.
| Stage | What happens | Who normally checks |
|---|---|---|
| Trial hole | A hole next to the footings shows the existing foundation and the ground | Structural engineer or surveyor |
| Each excavation | One short section is dug out under the old footing to the engineer’s depth | Design engineer and building control surveyor, before concreting |
| Concreting | The section is filled with concrete to the engineer’s specification | Builder, to the engineer’s details |
| Packing | Sand and cement packing is rammed into the gap between the new concrete and the old footing | May also be inspected by the engineer and building control surveyor |
| Completion | The last section is finished and any drains are reinstated | Building Control final inspection, then the completion certificate |
The packing matters. The Planning Portal points out that filling the hole with concrete does not on its own guarantee firm support, because gaps can be left between the new concrete and the old foundation. Ramming in a sand and cement packing closes that gap.
Underpinning is risky if it is done badly. The Planning Portal warns that it can damage or even collapse the existing home, and advises using experienced people for both the design and the building work.
The Party Wall Act
The Party Wall etc. Act 1996 applies in England and Wales and is separate from building regulations. Underpinning often comes under it, either because the wall being underpinned is shared with a neighbour, or because the digging is close to a neighbour’s building.
| Work | Part of the Act | Notice to give |
|---|---|---|
| Underpinning the whole thickness of a party wall | Section 2 | At least two months before work starts |
| Digging within 3 metres of a neighbour’s building and deeper than its foundations | Section 6 | At least one month before work starts |
| Digging within 6 metres of a neighbour’s building where the hole crosses a line drawn down at 45 degrees from the bottom of its foundations | Section 6 | At least one month before work starts |
The GOV.UK booklet says a notice is only valid for a year, so it should not be served too early. If the neighbour has not replied within 14 days, a dispute is treated as having arisen and the Act’s surveyor procedure applies. Starting work without giving notice properly can lead to a court injunction stopping the work.
Send us the address, a few photos of any cracks and what you know about the house. We can arrange the structural engineer, any site investigation and the building control application, and see it through to the completion certificate.
After the work
When Building Control is satisfied, it issues a completion certificate. Keep it with the engineer’s design and calculations. When you sell, the buyer’s solicitor is likely to ask about any structural work, and these papers answer that. Our completion certificate guide explains what to do if the certificate is missing.
If underpinning was done in the past without approval, Building Control can sometimes approve it after the event. Our regularisation certificate guide explains how that works.
Frequently asked questions
Do you need building regs for underpinning?
Yes. The Building Regulations 2010 name “work involving the underpinning of a building” as building work, so it needs approval from the council’s building control team or a registered building control approver.
Does underpinning need planning permission?
Usually not. The Planning Portal says maintenance on foundations generally does not need planning permission. Check with the council first if the building is listed or in a conservation area, national park or area of outstanding natural beauty.
Do I need a structural engineer for underpinning?
Yes. Approval normally needs a structural design for the underpinning, including how it will be carried out, and each excavation is normally inspected by the design engineer before it is concreted.
Can any builder do underpinning?
The Planning Portal advises using people with experience of underpinning, because badly done work can damage or collapse the house. The builder should follow the engineer’s design and order of work exactly.
What does Building Control inspect?
Each section of excavation is normally inspected by the design engineer and a building control surveyor before it is concreted. The packing between the new concrete and the old footing may also be inspected, then there is a final inspection before the completion certificate.
Should underpinning be done every 40 years?
No. There is no rule that underpinning has to be redone after a set number of years. It is designed as a lasting fix for the cause of movement found at the time. If new cracks appear later, get an engineer to look at the cause.
Does the Party Wall Act apply to underpinning?
Often, yes. Underpinning a shared wall needs at least two months’ notice under section 2. Digging within 3 or 6 metres of a neighbour’s building, depending on depth, needs at least one month’s notice under section 6.
Do I have to tell a buyer about underpinning?
Expect the buyer’s solicitor to ask about any structural work when you sell. Have the completion certificate and the engineer’s design ready. Your own solicitor can tell you exactly what the property forms ask.
Get a Free Quote for Your Project
Send us the address, a few photos of any cracks and what you know about the house. We can arrange the structural engineer, any site investigation and the building control application, and see it through to the completion certificate.
Last reviewed: November 2026. Checked against regulation 3 of the Building Regulations 2010 (legislation.gov.uk), the Planning Portal’s underpinning pages and the Party Wall etc. Act 1996 explanatory booklet (GOV.UK). General guidance for England only. Get project-specific advice before relying on it.