A trial pit is a hole dug to see what is really under the ground before you build. For an extension it usually means checking the depth and condition of the existing foundations, and the soil the new ones will sit on. This guide explains when you need one, what is recorded and how it fits with building control.

Free quotesSend your drawings for a price
6-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm

Foundations are designed for the ground they sit on. Drawings and maps can only tell you so much, so building control, structural engineers and warranty providers often ask for a trial pit to confirm the ground before the foundations are signed off. It is the simplest kind of ground investigation, and often the cheapest way to avoid a surprise once the digger is on site.

Developer guide

Two kinds of trial pit

01

Foundation inspection pit

Dug against the wall of an existing building to show how deep its foundation goes, how wide it is, what it is made of and what it sits on. Used for extensions, underpinning, new storeys and loft conversions that add weight to old walls.

02

Ground investigation pit

Dug where the new building will go to show the layers of soil, how firm they are, whether there is water, roots or made ground, and to take samples for testing.

Many extensions need both: one pit by the house to see the old foundation, and one in the footprint of the extension to see the ground the new foundation will sit on.

Do you need one?

When you are likely to need one

01

Clay near trees

Clay shrinks and swells as trees take up water, so foundations near trees usually have to go deeper. The depth depends on the type of clay, which is tested from samples.

02

Unknown or filled ground

Old gardens, former buildings, ponds or tipped material can hide soft ground that needs a deeper or different foundation.

03

Building next to an old house

The new foundation often has to match or go below the existing one, so its depth needs to be known.

04

Adding weight to existing walls

A new storey, a loft conversion with steel beams or a heavier roof can mean checking the foundations below can take it.

05

Sloping sites and retaining walls

Where ground levels change, the engineer needs to see the soil before designing walls or stepped foundations.

06

Building control asks

If the ground is not clear from local knowledge, a building control surveyor can ask for a trial pit before approving the foundation design.

Developer guide

What gets recorded

A trial pit is only useful if it is properly logged. The engineer or ground specialist records:

  • The depth of the pit and of each layer of soil, with a description of each
  • For an inspection pit, the depth, width and make-up of the existing foundation and what it bears on
  • Any groundwater, and the level it settles at
  • Roots, with their depth and size, and nearby trees
  • Made ground, rubble or anything unexpected
  • Samples taken for laboratory tests, such as clay tests where trees are close
  • Photos of the pit and its sides

The engineer then uses the log to design the foundation, and it goes to building control with the structural calculations. See our Structural Engineering service for the design side.

Need the pit logged for Building Control?

We can arrange the digging, the logging and the engineer’s foundation advice together, so building control gets everything in one go.

Developer guide

Trial pits or boreholes?

Trial pit Borehole or window sample
How it works An open hole dug by hand or with a small digger A narrow hole drilled or driven by a rig
Depth Shallow, a few metres at most Much deeper where needed
What you see The soil and existing foundations in place Soil brought up as samples
Usual use Extensions, small new builds, checking existing foundations Larger buildings, soft or deep ground, piled foundations

For a house extension a trial pit is usually enough. For new homes, flats or commercial buildings, a fuller site investigation with boreholes or window sampling is more common, often after a desk study. Our guide Do I need a ground investigation? explains when.

Developer guide

Can I dig one myself?

For a simple extension, a builder sometimes digs the pit and building control comes to look at it. That can work, but bear in mind:

01

Buried services

Check for gas, water, electric and drainage before anyone digs. Our guide Do I need a utility survey? explains how.

02

Safety

Never climb into an unsupported pit. The sides can collapse without warning, and a pit next to a house can undermine its foundation if left open.

03

Someone has to read it

A hole on its own proves little. The soil has to be described, measured and sometimes tested, and the engineer has to turn that into a foundation design.

04

Backfill

Fill the pit back in properly, in layers, so it does not leave a soft spot where the new foundation will go.

How it works

The process, step by step

  1. Send us the site address, drawings and what Building Control or your engineer has asked for.
  2. We agree where the pits go and how many are needed.
  3. Buried services are checked before digging.
  4. The pits are dug, logged, photographed and sampled where needed.
  5. The pits are backfilled and the site left safe.
  6. You get the trial pit log and, if needed, the engineer’s foundation advice.
  7. The log goes to Building Control with the foundation design.
Your questions

Frequently asked questions

What is a trial pit?

A hole dug, by hand or with a small digger, so the soil and any existing foundations can be seen, measured and recorded before new foundations are designed.

Do I need a trial pit for an extension?

Not always, but it is common. Building control or your engineer may ask for one where the ground is unknown, there are trees on clay, or the depth of the house foundation needs to be known.

How deep should a trial pit be?

Deep enough to answer the question being asked. For an inspection pit, that means below the bottom of the existing foundation. For new foundations, it means below the depth the new foundation is expected to reach. The engineer sets the depth for each pit.

Can I dig a trial pit myself?

Sometimes, for a simple extension, if building control is happy to inspect it. Check for buried services first, never climb into an unsupported pit, and have it logged by someone who can describe the soil properly.

What is a foundation inspection pit?

A trial pit dug against an existing wall to show how deep and wide its foundation is, what it is made of and what it sits on. It is often needed before an extension, underpinning or adding a storey.

Is a trial pit the same as a soakaway test?

No. A soakaway test also uses a pit, but it is filled with water to measure how fast the ground drains, for designing a soakaway. A trial pit is about what the ground is made of and what it can carry.

How much does a trial pit cost?

It depends on how many pits are needed, how deep they go, access for a digger and whether samples need testing. Send us your drawings and site address for a free quote.

Get a Free Quote for Your Project

Send us the site address, your drawings and what building control or your engineer has asked for, and we will arrange a free quote.

Last reviewed: November 2026. Checked against Approved Document A (Structure) on GOV.UK. General guidance for England only. Get project-specific advice before relying on it.

Not sure what else your project needs?Answer three questions and get the full checklist, then one quote for the lot.
Try the services finder
Call usGet a free quote