About the project
This job was two 1.5-storey, two-bedroom detached dormer bungalows on land behind Lychgate Lane in Burbage, Hinckley.
We were instructed on building control, the 10-year structural warranty and a Phase 1 desk study.
Foundations went in from April 2022 at about 1.4m deep in medium shrinkable clay. Substructure blockwork and drainage followed in July, the superstructure reached second lift in August and the roof trusses were up by September. We carried out eight visits in all, the last in March 2023.