The story of the job
This job replaces an existing office building on High Street, Harrow with a six-storey residential block of 33 apartments. It came to us through a recommendation from a new client.
We manage and coordinate Building Control through a registered partner, along with the 10 Year Structural Warranty. Our visits started in December 2024 with a site meeting to agree the warranty stages, while the site strip was under way to evaluate the formation level.
The structure is reinforced concrete and the visits have followed it up the building. Reinforcement was checked to the structural engineer's design at the base, then at the columns and lift, then floor by floor, with concrete cover checked as it went.
By August 2026 the floor 6 reinforcement was in. At the October 2026 visit the external steel framing system was installed, with 15mm fire board to the external face and fire-rated insulation in the frame. The job is still running, with 12 visits so far.