Chimney Breast Removal

Removing a chimney breast is structural work. Whatever is left above, whether that is the breast upstairs, the stack in the loft or the chimney above the roof, still has to be held up. That means a support design, building regulations approval before you start, and often a party wall notice to your neighbour. This guide explains what is needed, the support options councils accept, and what to do if a breast was taken out years ago without approval.

Free quotesSend your drawings for a price
8-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm

The rules below are for England. Building control is not optional for this work: a chimney that is left without proper support can drop through a ceiling or pull a party wall out of line, sometimes years after the work was done.

Do you need one?

Do you need building regulations approval?

Yes. Taking out a chimney breast, or part of one, changes how the building carries its loads, so it counts as a material alteration under the Building Regulations 2010. The work has to meet Part A (structure) and must not make the building worse on fire safety or the neighbour’s flue. Councils such as Redbridge and Thurrock say plainly that a building regulations application is needed before the work starts.

You can apply to the council or to a Registered Building Control Approver. Either way, the support design should be approved before anything is taken out. Our guide to when you need Building Control covers the wider rules.

Developer guide

What has to be supported

01

Ground floor breast removed

The breast on the first floor, the stack in the loft and the chimney above the roof all still sit on it. This is the case that most needs a proper support design.

02

First floor breast removed

The loft stack and the chimney above the roof still need holding up, and the ground floor breast below is left in place.

03

Loft stack removed

Usually done with the chimney above the roof, so the roof is made good. The breasts below can stay.

04

Everything removed

Taking the whole chimney out, from ground to roof, removes the load altogether but means roof work and making good on every floor.

Redbridge Council’s guidance adds that the part of the breast left inside the house below the roof should be at least as tall as the brickwork of the stack above the roof.

Developer guide

Support options councils accept

01

Steel beam on padstones

A steel beam under the remaining brickwork, bearing on padstones in the walls either side. This is the most widely accepted option and normally needs a structural engineer’s calculations.

02

Steel beam and post

Where one side has no suitable wall to bear on, a steel post carries that end down to a sound base.

03

Gallows brackets

Steel angle brackets bolted into the wall under the remaining breast. Some councils accept them for small breasts in two-storey houses; others will not, and the rules differ from council to council.

04

Corbelling

Building the brickwork out in steps to carry what is above. Most councils, Redbridge and Thurrock among them, say this should not be used for breast removal.

Before work starts the engineer also checks whether the breast is doing another job. A chimney can act as a buttress to a long wall, and some older terraces have cross-over flues, where flues from both houses pass through the same breast. Redbridge’s guidance says a breast with cross-over flues cannot be removed.

Do you need one?

Gallows brackets: when they are allowed

Each council sets its own limits. As examples:

Council Its conditions for gallows brackets
Redbridge House no more than two storeys; brickwork party wall at least 215mm thick and sound; breast no more than 340mm deep and 1200mm wide; the neighbour’s breast still in place; party wall notice served; backed by a design and pull-out tests
Richmond Breast sticks out no more than about a third of the wall’s thickness; not where the wall is in lime mortar or the neighbour’s flues are in line with yours
Thurrock One bracket per flue, so two brackets for a two-flue stack; check the brickwork before fixing; heavier stacks designed individually

If your neighbour has already taken out their side, brackets on your side are usually refused, because the wall then has little left to hold it. In that case councils normally expect a steel beam, or the chimney above the roof to be taken down and the roof made good.

Taking out a chimney breast?

Send us a photo of the breast on each floor, a rough measurement of its width and depth, and whether the house is terraced or semi-detached. We will give you a free quote for the calculations and the building regulations application.

Developer guide

Other building regulations points

01

Fire protection to steel

Redbridge asks for at least 30 minutes’ fire protection to beams and brackets unless they sit fully within the roof space. This is usually plasterboard boxing.

02

The party wall itself

Where bricks have been cut away, the wall between you and the neighbour must still resist fire and sound. Recesses are filled with brickwork of the same thickness, and damaged bricks replaced.

03

The neighbour’s flue

If the neighbour still uses their chimney, any damage to the flue can let smoke or carbon monoxide into either house. Redbridge asks for the neighbour’s flue to be smoke tested after the work.

04

Capping and venting

A disused chimney that is left above the roof is capped with a vented cowl, and an air brick is fitted low down, so that the flue stays dry.

05

The floor

Where a hearth is taken out upstairs, the old trimmer joists come out and new joists are fitted across the gap.

Developer guide

Party wall notices

If the chimney breast is on a wall shared with your neighbour, the work is covered by the Party Wall etc. Act 1996. The government’s explanatory booklet gives “removing a chimney breast” as an example of section 2 work. You must serve notice at least two months before the work starts. Your neighbour then has 14 days to agree in writing; if they do not reply, a dispute is treated as having arisen and surveyors are appointed. A notice is valid for a year.

The Party Wall Act is separate from building regulations. An approval from building control does not replace the notice, and an agreement with your neighbour does not replace building regulations approval.

Developer guide

Planning permission and listed buildings

Taking out a chimney breast inside a house does not usually need planning permission. Removing or lowering the chimney above the roof can do, especially in a conservation area or where permitted development rights have been removed. A listed building needs listed building consent for either. Check with the council’s planning team before you take down an external stack.

Developer guide

What if it was removed years ago?

A chimney breast removed without approval is one of the most common things a buyer’s surveyor or solicitor picks up when a house is sold. Signs are a stack still showing above the roof with no breast inside, or brackets visible in the loft.

01

Get it checked

A structural engineer looks at how the remaining chimney is supported and whether that support is adequate.

02

Put it right if needed

If the support is missing or weak, a beam or brackets are fitted to an approved design.

03

Get it signed off

The council can issue a regularisation certificate for work done on or after 11 November 1985. Only the council can do this, not an approver. Our regularisation certificate guide explains the steps, including opening up so the surveyor can see the support.

Your questions

Frequently asked questions

Do I need building regulations to remove a chimney breast?

Yes. It is structural work, so you need building regulations approval before you start, from the council or a Registered Building Control Approver. The design for supporting what is left above has to be approved.

Do I need a structural engineer to remove a chimney breast?

For a steel beam, yes: councils expect calculations from a structural engineer. Some councils accept standard gallows brackets for small breasts in two-storey houses without full calculations, but others, such as Redbridge, ask for a design and pull-out tests even for brackets.

Can I use gallows brackets?

Sometimes. It depends on your council, the size of the breast, the thickness and condition of the wall, and whether your neighbour has removed their side. Many councils now prefer a steel beam. Ask before you buy brackets.

Do I need to tell my neighbour?

If the breast is on a shared wall, yes. Removing a chimney breast from a party wall is section 2 work under the Party Wall etc. Act 1996, and you must serve notice at least two months before starting.

Do I need planning permission to remove a chimney?

Not usually for a chimney breast inside the house. Removing the chimney above the roof may need planning permission in a conservation area, and any work to a listed building needs listed building consent.

What happens if a chimney breast was removed without approval?

Have a structural engineer check the support, put it right if needed, and apply to the council for a regularisation certificate. A buyer’s solicitor will usually ask for this when you sell.

Can I remove the chimney breast if my neighbour has removed theirs?

Possibly, but not usually with gallows brackets. With both breasts gone, councils normally expect a steel beam, or for the chimney above the roof to be taken down and the roof made good.

Does a removed chimney breast affect a house sale?

It can. Surveyors look for a chimney above the roof with no breast below it. Without a completion or regularisation certificate, buyers may ask for one, for indemnity insurance or for a lower price.

Get a Free Quote for Your Project

Send us a photo of the breast on each floor, a rough measurement of its width and depth, and whether the house is terraced or semi-detached. We will give you a free quote for the calculations and the building regulations application.

Last reviewed: November 2026. Checked against the government’s Party Wall etc. Act 1996 explanatory booklet on GOV.UK and the chimney removal guidance published by Redbridge, Richmond and Thurrock councils. Each council sets its own conditions. General guidance for England only. Get project-specific advice before relying on it.

Not sure what else your project needs?Answer three questions and get the full checklist, then one quote for the lot.
Try the services finder
Call usGet a free quote