What Is a BRUKL Report?
A BRUKL report is the short Part L report that Building Control asks for on every new commercial building. It comes out of the SBEM calculation and shows whether the building’s energy use and carbon emissions are within the targets. This guide explains what is in it, when you need each version, what a fail means and how to fix one. SBEM calculations, including both BRUKL reports, are From £250 + VAT.
In this guide
What does BRUKL stand for?
BRUKL stands for Building Regulations UK Part L. Part L is the part of the Building Regulations that covers the energy use and carbon emissions of buildings.
The BRUKL report is a standard output from the approved software used to check a building that is not a home, such as a shop, office, warehouse, school or hotel. That software is usually SBEM, the Simplified Building Energy Model, or for more complex designs another approved package such as a dynamic simulation model. Homes use SAP instead, and SAP produces its own report. Our SAP or SBEM guide explains which one your project needs.
You cannot have a BRUKL report without the calculation behind it. The energy assessor builds a model of your building in the software, and the BRUKL report is the summary of that model that Building Control reads.
What does a BRUKL report show?
The software compares your building with a notional building. That is the same size and shape as yours, with standard walls, windows, heating, lighting and so on set by the government’s National Calculation Methodology. The notional building sets your targets. The report then shows:
Target primary energy rate
How much primary energy the notional building would use each year, per square metre of floor. Your figure for this is the building primary energy rate, and it must not be higher than the target.
Target emission rate
The carbon dioxide the notional building would give off each year, per square metre. Your figure is the building emission rate, and again it must not be higher than the target.
Building fabric
The U-values of your walls, roof, floors, windows and doors, checked against the limiting values in Approved Document L.
Building services
The heating, hot water, cooling, ventilation and lighting, checked against the minimum efficiencies Approved Document L sets.
Air permeability
The airtightness figure used in the model. At the end of the job this is replaced with the measured result of the air test.
List of specifications
The construction and equipment the result is based on. This is what Building Control checks the finished building against.
A pass needs all of it. A building can beat both targets and still fail because one item, such as a rooflight or a boiler, is below the minimum standard.
Design-stage and as-built BRUKL reports
Approved Document L asks for two versions of the report, made at two points in the job.
| Version | Due | Based on |
|---|---|---|
| Design stage | By the day before work starts | The drawings and the planned specification |
| As-built | Within five days of completion | What was really built, the air test result and any changes |
The as-built report is signed twice: by the energy assessor, to confirm the calculation is accurate, and by the client, usually the developer, to confirm the building was built to the specification in the report.
Higher-risk buildings follow a different process: the design figures go in with the building control application and the as-built figures with the application for a completion certificate.
The design-stage report is also the cheapest time to find a problem. A fail on paper can be fixed by changing the specification. A fail at completion can mean changing equipment that is already fitted.
What if the BRUKL report says the building fails?
A fail means one of three things: the building primary energy rate is above its target, the building emission rate is above its target, or an element or system is below the minimum standard. The report shows which. The usual ways to fix it are:
Better fabric
More insulation in the walls, roof or floor, or better windows and rooflights, to bring the U-values down.
Less heat loss through gaps
Design for a better airtightness figure, then make sure the build achieves it on the day of the air test.
More efficient heating and hot water
A heat pump in place of a boiler can make a big difference to both targets.
Better lighting and controls
Efficient LED lighting, daylight and occupancy controls, and good heating controls all count in the model.
On-site renewables
Solar panels lower the building’s energy and carbon figures.
Glazing and overheating
Large areas of glass can push the cooling up in summer. Shading or a different glass can help.
The assessor can test changes in the model before anything is ordered, so you can pick the cheapest mix that passes. If something changes on site, such as the heating plant, the lighting or the glazing, tell the assessor early, because the as-built result changes with it.
BRUKL reports under the 2026 rules
A new edition of Approved Document L Volume 2 takes effect on 24 March 2027 in England, and on 24 September 2027 for higher-risk building work. This is often called the Future Buildings Standard. The BRUKL report stays: there is still a design-stage report and an as-built report, signed in the same way. What changes is the notional building, which the SBEM software and the National Calculation Methodology are being updated to match, so the targets your building has to beat change too.
Your project can stay on the current rules if a building notice, initial notice or full plans application goes to Building Control before 24 March 2027 and work on that building starts before 24 March 2028. If your project is near that date, ask for the design-stage SBEM to be run against the new rules as well. Our SBEM calculations page explains what the new rules expect.
BRUKL reports and the commercial EPC
The BRUKL report and the EPC are different documents, but they come from the same model. The BRUKL report shows Building Control that the building meets Part L. The EPC rates the finished building from A to G for buyers and tenants, and it has to be lodged by an accredited energy assessor. Once the as-built SBEM is done, the EPC normally follows from it, so it makes sense to have one assessor do both.
What we need to produce your BRUKL report
Drawings
Floor plans, sections and elevations, with the use of each room or zone marked.
Construction
Wall, roof and floor build-ups, and the window and door specification.
Services
The planned heating, hot water, ventilation, cooling and lighting, and any solar panels.
Location and use
The site address and what the building will be used for.
If parts of the design are not settled yet, the assessor can model a sensible specification and show you what it has to achieve. See our SBEM cost guide for what changes the price, and our L2B SBEM page for extensions and conversions of existing buildings.
Frequently asked questions
What is a BRUKL report?
It is the Part L compliance report produced by the SBEM calculation, or by other approved software, for a building that is not a home. BRUKL stands for Building Regulations UK Part L. Building Control uses it to check that the building’s energy use and carbon emissions are within the targets and that the fabric and services meet the minimum standards.
Is a BRUKL report the same as an SBEM?
No. SBEM is the calculation and the BRUKL report is the summary it produces. You cannot have the report without the calculation, so when someone asks for a BRUKL report they need an SBEM, or an approved alternative, done first.
When do I need a BRUKL report?
For a new building that is not a home, twice: a design-stage report, which Building Control must have no later than the day before work starts, and an as-built report no later than five days after the work is complete. Some extensions and changes of use of existing commercial buildings also need one.
Who signs the BRUKL report?
The as-built report is signed by the energy assessor, to confirm the calculation is accurate, and by the client, usually the developer, to confirm the building was built to the specification in the report.
Does a house need a BRUKL report?
No. Homes are checked with SAP calculations, which produce their own compliance report. A BRUKL report is for buildings other than homes. A mixed-use scheme, such as flats over shops, usually needs both.
What happens if my BRUKL report fails?
Building Control will not accept it as it stands. The assessor changes the specification in the model, for example insulation, glazing, heating, lighting or solar panels, until the building passes, and then issues a new report. Finding this at design stage is far cheaper than at completion.
Does the BRUKL report give me an EPC?
Not by itself. The commercial EPC is a separate certificate, but it is normally produced from the same as-built model, so the two are usually done together by the same accredited assessor.
How much does a BRUKL report cost?
The BRUKL report comes with the SBEM calculation. SBEM calculations are From £250 + VAT, which covers the design stage, the as-built stage and the EPC. Guide price. Get a free quote for your project.
Get a Free Quote for Your Project
Send us your drawings and specification and our accredited energy assessors will run the SBEM and produce the design-stage BRUKL report.
Last reviewed: November 2026. Checked against Approved Document L Volume 2 (2021 edition, and the 2026 edition that takes effect on 24 March 2027), including Appendix C and regulation 27 of the Building Regulations 2010. Every building is different, so your targets and result come from the SBEM model for your design.