TM59:2026 is the new version of the CIBSE method for checking whether a new home will overheat. It was published in July 2026 and changes how bedrooms are judged, which weather is used and the order in which fixes are tried. For Part O sign-off today, though, the 2017 version is still the one required. This guide explains what has changed and what it means for your project.

Free quotesSend your drawings for a price
7-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm

TM59 is a computer model of how hot each room gets through a summer. Since 2022 it has been one of the two ways to show a new home meets Part O of the Building Regulations, the overheating rule. CIBSE, the body that writes the method, has now updated it for the first time since 2017, drawing on nearly ten years of use and new research on sleep and heat. Planning conditions, funders and clients can ask for it, so it is worth knowing what it involves.

Developer guide

The short answer for Part O

Approved Document O (2021 edition, in force since 15 June 2022) still names TM59 (2017), and CIBSE says the 2017 version is still required for Part O. CIBSE recommends the 2026 version as best practice and says it is talking to the Building Safety Regulator about bringing the new method and weather files into the Approved Documents. No date has been set for that.

01

Building control sign-off

TM59 (2017), the version Approved Document O names today.

02

Planning conditions

Read the wording. If a condition names TM59:2026, the report needs to follow it.

03

Funders and clients

Some ask for the newer method. Check your brief or employer’s requirements.

04

Larger or longer projects

Testing the design against both versions early can avoid a redesign if the rules move during the build.

Been asked for TM59:2026?

Send us your drawings, the site address and the wording of the planning condition or brief, and we will arrange a free quote for the right version.

Developer guide

What has changed in TM59:2026

01

A new bedroom test

The old test counted the hours a bedroom was over 26°C at night. The new one looks at the average temperature each night. For most homes, a bedroom fails if that average is over 27°C on more than four nights between May and September. It is based on recent Loughborough University research on sleep.

02

Three stages, in order

Stage 1 models the home with windows free to open and no limits. Stage 2 adds the real limits of the site, such as noise, security and air quality. Stage 3 allows cooling, but only if the first two stages cannot pass.

03

Future weather

Homes must be tested, as a minimum, against a warm summer as expected in the 2050s, not just today’s weather. Heatwave years are recommended too.

04

New weather areas

Weather data now comes from 28 zones covering the UK, instead of the nearest individual weather station.

05

Corridors and shared areas

Communal corridors and spaces in blocks of flats now have to be assessed, and they count towards the overall result.

06

Ceiling fans

Fans are now formally credited, because moving air makes a room feel cooler for very little energy.

07

Home offices

There is now a standard pattern of use for a room used as a home office, so it is modelled the same way on every job.

08

Clearer reports

Reports follow a set checklist, so building control, planners and clients can see what was assumed.

Developer guide

TM59 (2017) and TM59:2026 side by side

Topic TM59 (2017) TM59:2026
Used for Part O Yes Not yet, best practice only
Bedroom test Hours over 26°C at night Average night temperature, nights over the limit counted
Weather Present-day summer from a nearby station 2050s summer as a minimum, from 28 UK zones
Order of fixes Not set out in stages Passive design, then site limits, then cooling last
Communal corridors Not required Assessed and counted
Ceiling fans No formal credit Formally credited
Home offices No set profile Standard profile
Developer guide

Will my home be harder to pass?

Often, yes. A 2050s summer is a tougher test than today’s weather, and the new order means you have to show passive measures were tried before cooling. The homes most at risk are the same ones that struggle now:

01

Single-aspect flats

With windows on one side only, there is no cross-breeze to carry heat out.

02

Large south or west glazing

Big windows let in a lot of sun in the afternoon and evening.

03

Noisy or busy sites

If windows cannot be left open at night because of road, rail or aircraft noise, the home has to stay cool another way.

04

Top floors and rooms under rooflights

These get the most sun and the least shade.

05

Long corridors in blocks of flats

Heat from pipes and the flats builds up where it has nowhere to go. These now count.

Developer guide

Design changes that help under either version

01

External shading

Overhangs, balconies, fins and shutters stop sun before it reaches the glass. Internal blinds do not count for Part O.

02

Glazing size and glass

Smaller or better-placed windows, or solar-control glass, cut the heat let in.

03

Bigger openings

More openable window area, or openings on two sides, lets heat out.

04

Secure night ventilation

Louvred or restricted openings that can be left open safely at night.

05

Ceiling fans

Now credited in the 2026 method, and cheap to run.

06

Heat from pipes

Insulating hot water and heating pipes in corridors and risers keeps shared areas cooler.

Changes like these are cheapest at the drawing stage. Modelling early, before the elevations are fixed, is the best way to avoid air conditioning being the only answer. See our guide on the simplified method or TM59 to check which route your home needs.

Getting a quote

What we need from you

01

Drawings

Floor plans, elevations and sections, with window sizes and how they open.

02

Site address

So the right weather zone is used.

03

Noise report

If there is one, as it decides whether windows can be counted as open at night.

04

Ventilation and heating details

The ventilation system, any MVHR and where pipes run.

05

Which version you need

The planning condition, funder or client wording that says which TM59 to use.

Your questions

Frequently asked questions

What is TM59:2026?

The updated CIBSE method for modelling overheating risk in new homes, published in July 2026. CIBSE recommends it as best practice, with a new bedroom test, future weather and a three-stage approach.

Do I need TM59:2026 for Part O?

Not at the moment. Approved Document O still names TM59 (2017), and CIBSE says the 2017 version is still required for Part O. You may still need TM59:2026 if a planning condition, funder or client asks for it.

What is the new bedroom test in TM59:2026?

Instead of counting hours over 26°C at night, it looks at the average temperature each night. For most homes, a bedroom fails if the average is over 27°C on more than four nights between May and September.

What are the three stages in TM59:2026?

Stage 1 tests the home with windows free to open. Stage 2 adds real limits such as noise, security and air quality. Stage 3 allows cooling, but only if the home cannot pass at the first two stages.

Which weather file does TM59:2026 use?

As a minimum, a warm summer as expected in the 2050s, taken from one of 28 weather zones covering the UK. Heatwave years are recommended as an extra check.

Does TM59:2026 apply to existing buildings?

CIBSE’s method covers new homes and major refurbishments, and includes a section on existing homes and retrofit. Part O itself only applies to new residential buildings.

Is TM59:2026 free to download?

Yes. At the time of writing, CIBSE lists the TM59 (2026) PDF as free to download from its website.

How much does a TM59 assessment cost?

It depends on the number of homes, how many need modelling and which version is asked for. Send us your drawings and site address for a free quote.

Get a Free Quote for Your Project

Send us your drawings, the site address and the wording of the planning condition or brief, and we will arrange a free quote for the right version.

Last reviewed: November 2026. Checked against CIBSE’s TM59 (2026) publication page and Approved Document O on GOV.UK. General guidance for England only. Get project-specific advice before relying on it.

Not sure what else your project needs?Answer three questions and get the full checklist, then one quote for the lot.