Converting a House into Flats
Turning a house into two or more flats is building work that needs Building Regulations approval, and in almost every case planning permission too. The law treats it as a material change of use, so the whole building has to meet a set list of rules on fire, sound, energy, ventilation, drainage and security. This guide explains what those rules are, which reports and tests you will need, and the order to do things in.
The points below come from regulations 5 and 6 of the Building Regulations 2010, Approved Documents B (fire), E (sound) and L (energy), and section 55 of the Town and Country Planning Act 1990. They apply in England.
Why a flat conversion is a material change of use
Regulation 5 of the Building Regulations lists the changes that count as a material change of use. Two of them cover a house conversion:
The building contains a flat where it did not before
This covers a single house split into flats for the first time.
The building has more or fewer homes than it did
This covers a building that already holds at least one home and ends up with a different number, such as one flat split into two.
Once the change is a material change of use, regulation 6 says the building must be brought up to the listed requirements of the regulations, even where parts of it are not being rebuilt. That is the big difference from an extension or a loft conversion, where only the new work is checked.
Planning permission
Section 55(3)(a) of the Town and Country Planning Act 1990 says using a building as two or more separate homes, where it was used as a single home, is a material change in the use of the building. That makes it development, so planning permission is normally needed before the flats are created. Councils often look at flat sizes, bin and bike storage, parking and the effect on neighbours, and many set their own space standards in the local plan.
Planning and Building Regulations are separate. Getting one does not give you the other, and the plans for both should match. If a condition has to be cleared before work starts, see our guide to pre-commencement conditions.
What the Building Regulations ask for
Regulation 6 lists the requirements a building must meet after a change of use. For a house turned into flats they include:
Fire safety (Part B)
Means of warning and escape, fire spread inside the building, roofs and access for the fire service. External walls are also checked on buildings over 15 metres tall.
Sound insulation (Part E)
Walls and floors between the flats, and between the flats and shared areas, must resist the passage of sound, and they are tested before completion.
Energy (Part L)
Walls, roofs and floors that are kept may need upgrading, poor windows replaced, and new heating and lighting must meet the current standards.
Ventilation (Part F)
Each flat needs the ventilation set out in Approved Document F.
Water and drainage (Parts G and H)
Cold and hot water, bathrooms, kitchens, water efficiency, foul drainage and bin storage.
Moisture and contaminants (Part C)
Condensation in walls and roofs, and ground gases such as radon where they apply.
Security (Part Q)
Doors and windows that someone could easily reach from outside must resist break-ins, including each flat’s front door.
Heating appliances, electrics and EV charging (Parts J, P and S)
Boilers and flues, electrical safety, and charge points where the new flats have parking. See our Part S guide.
Any new walls, floors, stairs, openings or steel beams are also building work in their own right, so structural calculations are usually part of the package.
Fire safety in converted flats
Approved Document B Volume 1 has a short section on conversions to flats. It says the existing construction should be reviewed, and warns that kept timber floors can make the fire resistance rules hard to meet. The standard depends on the height of the building:
| Converted building | Fire resistance for elements of structure |
|---|---|
| Up to three storeys | At least 30 minutes (REI 30) can be accepted, as long as the escape routes meet Section 3 of the Approved Document |
| Four storeys or more | The full standard in Appendix B of the Approved Document |
In practice that usually means upgrading the floors between flats, a protected stair or hall, fire doors onto the escape route and a fire alarm system designed for flats. Once the flats are occupied, the shared parts fall under the Fire Safety Order, so a Fire Risk Assessment is needed for the common areas. If any flat is let as a shared house, our HMO fire safety guide covers the extra rules.
If the building will be at least 18 metres or seven storeys tall with two or more homes, it becomes a higher-risk building and approval comes from the Building Safety Regulator instead. See our guide to Gateway 2 applications.
Sound insulation and testing
Approved Document E sets lower targets for flats formed by a change of use than for new-build flats, because old buildings are harder to treat. The walls and floors between flats should meet these values:
| Element | Converted flats | New-build flats, for comparison |
|---|---|---|
| Separating walls, airborne sound | At least 43 dB | At least 45 dB |
| Separating floors and stairs, airborne sound | At least 43 dB | At least 45 dB |
| Separating floors and stairs, impact sound | No more than 64 dB | No more than 62 dB |
Airborne figures are DnT,w + Ctr, where higher is better. Impact figures are L’nT,w, where lower is better. Flats formed by a change of use must be tested before completion. Building Control asks for a set of tests on the first flats due to finish in each group of similar construction, and at least one set for every ten flats after that. A set for flats with both a separating floor and wall is normally six tests. If a set fails, the cause has to be fixed and the rooms tested again. Our Sound Testing cost guide explains how sets are counted.
Energy: Part L and SAP
Approved Document L Volume 1 treats a new flat made from an existing building as a material change of use. Paragraph 11.7 sets what has to be done:
Kept walls, roofs and floors
If they are worse than the threshold U-values in Table 4.3, they should be upgraded to the improved values, as far as is technically possible and pays back within 15 years.
Old windows and doors
Those between heated and unheated space with a U-value worse than 3.3 should be replaced to current standards.
New elements
New walls, roofs, floors, windows and doors meet the standards for new work in existing homes.
Glazing
Openings in each new flat should be no more than 25% of its floor area, unless the SAP route below is used.
Heating and lighting
New or extended heating, hot water, controls and solar panels meet the current standards.
The Table 4.3 targets used most often:
| Kept element | Upgrade if worse than | Upgrade to |
|---|---|---|
| Roof | 0.35 | 0.16 |
| Wall with cavity insulation | 0.70 | 0.55 |
| Wall with internal or external insulation | 0.70 | 0.30 |
| Floor | 0.70 | 0.25 |
Values are U-values in W/m²K. Paragraph 11.8 gives a more flexible option for buildings with more than one home: a conversion SAP calculation can show that all the flats together use no more energy and give off no more carbon than if each had been upgraded element by element. That can let you keep features that are hard to upgrade, or use more glazing, as long as you make it up elsewhere. Each new flat also needs its own EPC when it is sold or let.
Send us the existing and proposed drawings and the number of flats. We can arrange Building Control, the conversion SAP calculations, sound testing, structural calculations and the fire risk assessment for the shared areas, with one project manager for the lot.
The usual order of work
Survey and plans
Measure the house and check floor build-ups, the stair and the party walls. Draw the flats with sizes that meet the council’s standards.
Planning permission
Apply for the change of use and clear any conditions that must be met before work starts.
Building Control application
Full plans is normally best for a conversion, because the fire, sound and energy design is checked before you build. See Private Building Control for the routes.
Design-stage reports
Conversion SAP calculations, structural calculations for any new openings or beams, and the ventilation and drainage design.
Build and inspections
Building Control inspects at key stages, such as the floor and wall treatments before they are covered.
Testing and completion
Sound tests, ventilation checks, the electrical certificate, the as-built SAP and the EPCs, then the completion certificate.
Frequently asked questions
Do I need building regulations to convert a house into flats?
Yes. Creating flats from a house is a material change of use under regulation 5 of the Building Regulations 2010, so you need Building Control approval and the building must meet the requirements listed in regulation 6, including fire, sound, energy and ventilation.
Do I need planning permission to split a house into flats?
Normally yes. Section 55(3)(a) of the Town and Country Planning Act 1990 says using a single house as two or more separate homes is a material change of use, which is development needing planning permission.
What sound insulation is needed between converted flats?
At least 43 dB airborne for separating walls and floors, and no more than 64 dB impact for floors and stairs, measured on site. New-build flats need 45 dB and 62 dB. The flats must be tested before completion.
What fire resistance do floors need in a flat conversion?
In a converted building of up to three storeys, Approved Document B accepts at least 30 minutes for the elements of structure if the escape routes meet its Section 3. Four storeys or more need the full standard in its Appendix B.
Do I need SAP calculations for a flat conversion?
Often, yes. Part L can be met by upgrading each element to the Table 4.3 targets, but for buildings with more than one home a conversion SAP calculation can show the flats as a whole perform as well. Each flat also needs an EPC before it is sold or let.
Does every flat need its own front door security?
Yes. Part Q applies when a building gains a flat, so doors and windows that someone could easily reach, including the door from the shared hall into each flat, must resist break-ins.
Is a flat conversion checked by the council or a private approver?
Either can check a house to flats conversion, as long as the building is not a higher-risk building. If it will be 18 metres or seven storeys or more with two or more homes, the Building Safety Regulator handles it instead.
What happens if the flats were created without approval?
You can apply to the council for a regularisation certificate, which may mean opening up floors and walls so they can be checked, and doing the sound tests. See our regularisation guide. Planning enforcement is a separate matter.
Get a Free Quote for Your Project
Send us the existing and proposed drawings and the number of flats. We can arrange Building Control, the conversion SAP calculations, sound testing, structural calculations and the fire risk assessment for the shared areas, with one project manager for the lot.
Last reviewed: November 2026. Checked against regulations 5 and 6 of the Building Regulations 2010, Approved Document B Volume 1 (2019 edition with amendments to 2026, paragraphs 6.5 to 6.7), Approved Document E (Table 0.1a and Section 1), Approved Document L Volume 1 (2021 edition, paragraphs 4.11 to 4.13 and 11.5 to 11.8, Table 4.3; the 2026 edition in force from March 2027 keeps the same approach) and section 55 of the Town and Country Planning Act 1990. General guidance for England only. Get project-specific advice before relying on it.