Shell and Core EPCs

A shell and core building is a new commercial building, or unit, that is finished on the outside and in the shared areas but left without heating, cooling or lighting in the space a tenant or buyer will fit out. It still needs an EPC when it is built, sold or let. This guide explains how that EPC is worked out, what Part L asks of the developer and the tenant, and the rules on marketing, renting and penalties.

Free quotesSend your drawings for a price
9-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm

The points below come from the government’s guide to EPCs for the construction, sale and let of non-dwellings (GOV.UK), Approved Document L Volume 2 (2021 edition, and the 2026 edition that replaces it) and the GOV.UK guidance on minimum energy standards for rented commercial property. They apply in England.

Developer guide

What shell and core means

Offices, shops, industrial units and mixed-use schemes are often built speculatively. The developer builds the frame, roof, walls, windows and the shared parts such as entrances, stairs and lifts. The space each occupier will use is handed over as a shell, and the occupier puts in their own heating, cooling, ventilation, lighting and finishes to suit their business.

Because the services are missing when the unit is finished, people often assume no EPC is possible. The GOV.UK guide says the opposite: if the unit will be fitted out and energy is expected to be used to heat or cool it, an EPC should be provided.

Do you need one?

Does a shell unit need an EPC?

Yes, in most cases. The GOV.UK guide says this applies whether a building has never had fixed services or is newly built on a shell and core basis. The things that decide it:

01

Construction

When a new building is physically complete, the person carrying out the work must give the owner an EPC and recommendation report and tell Building Control this has been done. Building Control will not issue a completion certificate until it is satisfied.

02

Sale or letting

An EPC must be available free of charge to anyone thinking of buying or renting the unit, at the latest when they ask for written information or view it.

03

Splitting a building

If a building is changed to have more or fewer parts for separate use, and the work provides or extends heating, hot water, air conditioning or mechanical ventilation, an EPC is needed on completion.

04

No conditioning at all

A building whose only heating or cooling is for a process, not for the people in it, does not need an EPC.

How it works

How a shell EPC is worked out

A commercial EPC comes from an SBEM calculation (or approved software) by an accredited non-domestic energy assessor. For a shell, the services that are not yet fitted have to be assumed.

The GOV.UK guide says the EPC should be based on the most energy-hungry fit-out that Part L allows for the building’s planning use class. Where no services are installed, the calculation falls back to the worst energy rating Part L allows. When the occupier fits out the unit, their work must meet Part L too, so the result should be the rating on the EPC or better.

In practice this means a shell EPC is a cautious rating. A unit fitted out with efficient heat pumps and LED lighting may well score better once it is done, but that only shows on a new EPC.

Developer guide

What Part L asks of the developer

Approved Document L Volume 2 has a section on shell and core developments. Both the 2021 edition and the 2026 edition say the same things in substance:

01

Design stage

The developer calculates the target and actual primary energy rates and emission rates for the building and sends them to the building control body. The 2026 edition says these should be based on a realistic fit-out that meets the energy rules.

02

Services not fitted

Where systems will be left out, reasonable assumptions are made for their efficiency, and the specification sent to Building Control lists the missing services, the efficiencies assumed and how there will be access to fit them later.

03

Completion of the base build

The as-built calculation is based only on what has actually been built. The fit-out areas are assumed to be heated to suit their use, but with no energy demand counted for them.

04

Logbook

When first fit-out happens, the building logbook should be updated and given to the building owner.

Stage What is needed Who normally arranges it
Before work starts Design-stage SBEM calculation (BRUKL report) with the assumed fit-out, sent to Building Control Developer, through their energy assessor
Base build complete As-built SBEM on what was built, then the EPC and recommendation report given to the owner Developer or main contractor
Marketing the unit EPC commissioned before marketing and shown to anyone interested Seller or landlord, and their agent
Tenant’s first fit-out New calculation sent to Building Control if heating, hot water, cooling or ventilation is added Tenant or their fit-out contractor
Developer guide

What the tenant’s fit-out has to do

Approved Document L treats the first fit-out of a shell as part of a new building. If the occupier provides or extends fixed heating, hot water, air conditioning or mechanical ventilation, a new set of energy calculations must go to Building Control when the work is complete, covering the part of the building they fitted out.

If the fit-out has none of those services, any lighting fitted should be at least as efficient as the lighting the developer assumed in their first submission. Later fit-outs, after the first one, follow the Approved Document L rules for existing buildings instead.

A fit-out that only adds services does not on its own trigger a new EPC under the EPC rules, unless the building is also split into more or fewer units. Landlords often choose to get a new EPC after fit-out anyway, as it can show a better rating than the shell one.

Building or letting a shell unit?

Send us the drawings, the planning use class and what will be left for the tenant. We can do the design-stage SBEM, the as-built calculation and the EPC, and the tenant’s fit-out calculation when the time comes.

Developer guide

Selling or letting the unit

The GOV.UK guide sets out the rules for anyone selling or letting a commercial building or unit:

01

Before marketing

The seller or landlord must commission an EPC before the unit goes on the market, and an agent must be satisfied that one has been commissioned.

02

Timing

All reasonable efforts must be made to get the EPC within 7 days, with a further 21 days allowed if it still cannot be obtained.

03

Adverts

The rating must be shown in commercial adverts and written particulars where an EPC is available.

04

How long it lasts

A commercial EPC is valid for 10 years, or until a newer one is lodged, and can be reused for later sales and lettings in that time.

05

Display

Buildings over 500 square metres that are often visited by the public must display their EPC where one has been produced.

Penalties

Trading Standards enforces the rules on sale and letting. The penalty for not making an EPC available is usually 12.5% of the building’s rateable value, with a minimum of £500 and a maximum of £5,000. Where that formula cannot be used, the default is £750. Failing to give a copy to an enforcement officer within 7 days of being asked is a further £200.

Developer guide

Minimum ratings for rented commercial property

The Energy Efficiency (Private Rented Property) Regulations 2015 set a minimum rating for rented commercial property in England and Wales. GOV.UK says that since 1 April 2018 a landlord can only grant, extend or renew a tenancy if the property is rated at least E, and since 1 April 2023 this applies to all rented commercial property, even with no change of tenant, unless a valid exemption is registered.

The rules do not apply to lettings of 6 months or less (with some exceptions) or of 99 years or more. Because a shell EPC assumes the least efficient fit-out Part L allows, it is worth checking the design-stage rating early, so the unit can be let without needing an exemption.

Your questions

Frequently asked questions

Does a shell and core building need an EPC?

Yes, if it will be fitted out and heated or cooled for the people using it. The GOV.UK guide says an EPC should be provided for units let as bare shells, based on the most energy-hungry fit-out Part L allows for the use class.

How can you rate a building with no heating installed?

The energy assessor assumes the services. Where none are installed, the calculation uses the least efficient fit-out Part L allows for that type of building, so the rating is cautious.

Who pays for the EPC on a shell unit?

The person carrying out the construction must give the EPC to the owner when the building is complete, so on a new development that is normally the developer or main contractor. A seller or landlord is responsible for having one before marketing.

Does the tenant need a new EPC after fit-out?

Not always under the EPC rules. A fit-out that adds services needs new Part L calculations for Building Control, but a new EPC is only required on completion if the building is also split or merged. Landlords often get one anyway, as it can show a better rating.

Can a shell unit be let if its EPC is F or G?

Not without a registered exemption. Rented commercial property in England and Wales must be rated at least E, unless the letting is 6 months or less, 99 years or more, or a valid exemption has been registered.

How long does a commercial EPC last?

10 years, or until a newer EPC is lodged for the building, if that comes first. It can be reused for sales and lettings within that time.

What is the fine for not having a commercial EPC?

Usually 12.5% of the rateable value, at least £500 and at most £5,000, with a £750 default where that cannot be worked out. Not handing a copy to Trading Standards within 7 days of a request is a further £200.

Is a shell and core EPC the same as a BRUKL report?

No. The BRUKL report comes from the SBEM calculation and shows Building Control that the building meets Part L. The EPC is the certificate lodged on the government register for buyers and tenants. Both normally come from the same calculation.

Get a Free Quote for Your Project

Send us the drawings, the planning use class and what will be left for the tenant. We can do the design-stage SBEM, the as-built calculation and the EPC, and the tenant’s fit-out calculation when the time comes.

Last reviewed: November 2026. Checked against the government’s guide to energy performance certificates for the construction, sale and let of non-dwellings (GOV.UK), Approved Document L Volume 2 (2021 edition, and the 2026 edition in force from March 2027) and the GOV.UK non-domestic minimum energy efficiency standard landlord guidance (updated May 2026). General guidance for England only. Get project-specific advice before relying on it.