Developer guide

Non-Material Amendments

A non-material amendment is the quickest way to make a small change to a scheme that already has planning permission, such as moving a window, changing a material or making the building slightly smaller. You apply to the council under section 96A of the Town and Country Planning Act 1990, there is no public consultation, and the council should decide within 28 days. This guide explains what counts as non-material, how it differs from a section 73 application, how to apply and what to do if the council says no.

Free quotesSend your drawings for a price
6-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm
Developer guide

What counts as a non-material amendment?

There is no legal definition. The government’s planning guidance says it depends on the scheme as a whole: a change that is non-material on one site can be material on another. The council has to be satisfied the change is non-material, and it must take into account the effect of the change together with any earlier non-material amendments to the same permission.

01

Usually accepted

Small changes that fit within what the permission describes, that do not breach any of its conditions and that do not make the building taller. The Planning Portal gives these as its examples.

02

Worth checking first

Changes that could affect neighbours, such as a new side window, or a run of small changes that add up.

03

Not suitable

Anything that changes the description of the development, breaches a condition or makes the building taller. These need a section 73 application or a new planning application.

Because it is the council’s judgement, a quick call or email to the planning officer before you apply often saves a refused application.

Developer guide

Non-material amendment, section 73 or a new application

Route When to use it What you get
Non-material amendment (section 96A) A genuinely small change to the approved scheme A written decision that is read alongside the original permission, which still stands
Section 73 application Changing or removing a condition, including a condition listing the approved drawings, for a minor material change A new permission with the new conditions, alongside the original one
New planning application Anything substantial, or a change to the description of the development A fresh planning permission

Section 73 cannot be used to extend the time limit for starting work or to change the description of the development. To use section 73 for a change to the drawings, the permission needs a condition that lists the approved drawings. If your permission has no such condition, the government’s guidance says you can use a non-material amendment to add one, and then use section 73 for the minor material change.

How it works

How to apply

01

The form

Use the standard application form, online through the Planning Portal or direct to the council.

02

Drawings

Send the revised drawings and a clear description of each change and how it differs from what was approved.

03

Telling the owners

Before you apply, you must notify anyone else who owns the land affected and any agricultural tenant. Tell them where the application can be seen and that they have 14 days to comment. Note on the form who you notified. There is no ownership certificate.

04

Consultation

The usual publicity and neighbour consultation rules do not apply, though the council can still choose to ask others.

05

The decision

The council should decide within 28 days, or longer if you agree in writing. The decision is in writing and covers only the changes you asked for.

A non-material amendment cannot be used to change a listed building consent. Changes to listed building works need a fresh listed building consent application.

Changing an approved scheme?

Send us the decision notice, the approved drawings and a sketch of the change. We will tell you which route fits, prepare the drawings and application, and update any reports that depend on the design, such as SAP, energy or drainage.

Prices

Fees

The council charges a fee. The Planning Portal currently lists £46 for householder development and £309 for any other development. Planning fees in England are due to change on 8 December 2026, so check the Planning Portal fee calculator or your council’s website before you pay. Our discharge of conditions page lists the related fees for changing a condition.

Developer guide

If the council refuses

There is no right of appeal against a refused non-material amendment, or if the council does not decide in time. The way forward is a section 73 application, if the change can be made through the conditions, or a new planning application. The original permission is not affected by a refusal, so you can still build what was approved.

Developer guide

Check the knock-on effects

A change to the drawings can affect other approvals that were based on them:

01

Planning conditions

Details already approved under a condition, such as materials or drainage, may need approving again if the change touches them. See our guide to discharging planning conditions.

02

Building regulations

Building control needs the revised drawings too, and the change may affect fire safety, structure or energy.

03

Energy and water calculations

Moving or enlarging windows changes the SAP or SBEM result, and a new bathroom layout can change the water calculation. Update them before the building is finished.

Your questions

Frequently asked questions

What is a non-material amendment?

A small change to a planning permission that the council agrees is not material, made under section 96A of the Town and Country Planning Act 1990. It changes the existing permission rather than creating a new one.

What is the difference between a material and a non-material amendment?

A non-material amendment is a change small enough that the council is satisfied it is not material in the context of the whole scheme. A material change needs a section 73 application or a new planning application.

How long does a non-material amendment take?

The council should decide within 28 days of a valid application, unless you agree a longer period in writing.

How much does a non-material amendment cost?

The Planning Portal currently lists £46 for householder development and £309 for anything else. Fees in England are due to change on 8 December 2026, so check before you apply.

Are neighbours consulted on a non-material amendment?

Not as a rule. The normal consultation and publicity rules do not apply, though the council can choose to ask others. You must notify any other owners of the land and any agricultural tenant, who have 14 days to comment.

Can I apply for a non-material amendment after the work is built?

The law does not rule it out, but the council still has to be satisfied the change is non-material. If it refuses, the route is a section 73 application or a new planning application. Ask the council before relying on it.

Can I appeal a refused non-material amendment?

No. There is no right of appeal. You would need to make a section 73 application or a new planning application for the change.

Can a non-material amendment change a listed building consent?

No. The procedure only applies to planning permissions. Changes to listed building works need a new listed building consent application.

Get a Free Quote for Your Project

Send us the decision notice, the approved drawings and a sketch of the change. We will tell you which route fits, prepare the drawings and application, and update any reports that depend on the design, such as SAP, energy or drainage.

Last reviewed: November 2026. Checked against the government’s planning practice guidance “Flexible options for planning permissions” on GOV.UK and the Planning Portal’s page on non-material amendments. General guidance for England only. Get project-specific advice before relying on it.