Developer guide

Regularisation Certificates

A regularisation certificate is how you get building regulations sign-off for work that was done without building control. You apply to the council, the council inspects what was built, you put right anything that does not comply, and the council then issues the certificate. This guide explains when you need one, how the process works, what it costs and what to do if you are selling.

Free quotesSend your drawings for a price
8-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm

Regularisation is set out in regulation 18 of the Building Regulations 2010. It covers work in England carried out on or after 11 November 1985 without a building notice, a full plans application or the required notice of start. Only the council can issue the certificate. A Registered Building Control Approver cannot sign off work after it has been done.

Do you need one?

When you need one

01

Work done without approval

An extension, loft conversion, garage conversion, removed wall or new window that should have had building control and did not.

02

Selling a home

The buyer’s solicitor asks for the completion certificate for past work, and there isn’t one because no application was ever made.

03

Remortgaging

A lender asks for proof the work was approved.

04

Peace of mind

You bought a home with unapproved work and want to know it is safe, and to have the paperwork for when you sell.

If the work was approved but the final certificate was never issued, you usually do not need regularisation. The original application is still open, so ask the council or approver to finish it. Our completion certificate guide covers that route.

How it works

How the process works

01

Apply to the council

Send a regularisation application with a description of the work and, where you can, a plan of it. Most councils have a form and ask for the fee when you apply.

02

Plans of anything extra

Where you can, also send a plan showing any extra work needed to make it comply. This often means drawings and structural calculations for beams, foundations or a roof.

03

Inspection

A building control surveyor visits. The council can ask you to open up the work so they can see it, carry out tests or take samples.

04

A list of what needs doing

The council tells you what work is needed to comply, that nothing more is needed, or that it cannot tell what is needed.

05

Put it right

You carry out the work on the list, and the surveyor checks it.

06

The certificate

Once the council is satisfied, it can issue a regularisation certificate.

The work is judged against the building regulations that applied when it was carried out, not today’s rules. A 2015 extension is checked against the 2015 rules.

Developer guide

What opening up means

A surveyor cannot see inside a finished wall, floor or roof. To check what is hidden, the council may ask you to expose parts of the work. Typical requests are:

01

Foundations

A small trial hole beside the wall to show the depth and width of the footing.

02

Steel beams

Plaster removed at the ends of a beam to show its size, its bearings and any padstones, with calculations to prove it is strong enough.

03

Insulation

A small section of ceiling, wall or floor lifted to show the type and thickness.

04

Drainage

A camera survey or a test of the new drains.

05

Electrics

An electrical installation condition report from a registered electrician.

06

Fire safety

For loft conversions, checks on fire doors, the protected stair and smoke alarms.

The surveyor decides how much opening up is needed. Good records, such as photos taken during the build, the builder’s invoices and any engineer’s calculations, can reduce it.

Developer guide

Regularisation or a completion certificate?

Completion certificate Regularisation certificate
When you apply Before the work starts After the work is done
Who can issue it The council, an approver or the Building Safety Regulator Only the council (or the Regulator for its own buildings)
Inspections During the build, at set stages After the build, often with opening up
Work it covers Work started on or after the application Unapproved work done on or after 11 November 1985
What it proves Evidence the work complies Evidence the work complies, but not conclusive

Both are accepted by most solicitors and lenders. The law says a regularisation certificate is evidence, but not conclusive evidence, that the work meets the rules.

Work done without Building Control?

Send us what was built, roughly when, and any photos, drawings or invoices you have. We will tell you what the council is likely to need and give you a free quote for the drawings, calculations and reports.

Prices

What it costs

Each council sets its own regularisation charge and publishes it in its building control charges list. It is usually higher than a normal application, because the surveyor has to work out what was built after the event. Add to that:

01

Drawings

Plans of the work as built, if you do not have them.

02

Structural calculations

For any beams, removed walls or new roof structure.

03

Opening up and making good

A builder to expose the work and then repair it.

04

Remedial work

Anything the council says must be changed, such as more insulation, a bigger beam or a fire door.

05

Test certificates

Electrical, drainage or air tightness tests where needed.

The council’s charge is often the smallest part. The real cost depends on how much has to be opened up and changed.

How it works

How long it takes

There is no fixed time in the regulations. It depends on how quickly the council can visit, how much opening up is needed and how long any remedial work takes. Simple cases with good records can be quick. A loft conversion with hidden steelwork and no paperwork takes longer. If you are selling, start as early as you can.

Developer guide

If you are selling or buying

A buyer’s solicitor may suggest indemnity insurance instead of regularisation. It is cheaper and quicker, but it does not check the work is safe. It only covers the cost if the council later takes action. Policies often stop covering you once the council has been told about the work, so speak to your solicitor before you contact the council.

Since 1 October 2023 the council can serve a notice to remove or alter work that breaks the building regulations for up to 10 years after the work was finished. Before then the limit was 12 months. Separately, the council or the Attorney General can still go to court for an injunction at any time, so the 10 years is not a full amnesty.

Developer guide

Work done before 11 November 1985

Regularisation does not cover work done before 11 November 1985. If you need comfort on older work, a survey by a building surveyor or a report from a structural engineer can show it is sound. Ask your solicitor what the buyer or lender will accept.

How it works

How we can help

We prepare what the council asks for: drawings of the work as built, structural calculations for beams and foundations, SAP calculations where insulation or windows need checking, and fire and drainage advice. We can also deal with the council on your behalf and manage the opening up, so you know what is needed before you start. See our Building Control service for new work, and Structural Engineering for calculations.

Your questions

Frequently asked questions

What is a regularisation certificate?

A certificate from the council confirming that building work done without building control meets the building regulations that applied when it was done. It is issued under regulation 18 of the Building Regulations 2010.

Can a private approver issue a regularisation certificate?

No. A Registered Building Control Approver can only take on work before it starts. Work already done without approval goes to the council.

Is a regularisation certificate as good as a completion certificate?

Most solicitors and lenders accept it in the same way. Both are evidence that the work complies. The law says a regularisation certificate is evidence but not conclusive evidence, which in practice is rarely a problem.

Do I need a regularisation certificate after 10 years?

Not by law, but you may still want one. After 10 years from completion the council can no longer serve a notice to remove or alter the work, but an injunction is still possible, and a buyer or lender may still ask for proof the work is safe. Regularisation remains available for any work done on or after 11 November 1985.

How much does a regularisation certificate cost?

The council’s charge is set by each council and is listed on its website. On top of that you may need drawings, calculations, opening up and remedial work. Send us the details for a free quote for our part.

What if the council finds problems?

It tells you what work is needed. You carry it out, the surveyor checks it, and then the certificate can be issued. If the work cannot be made to comply, the council can refuse the certificate.

Can I apply for regularisation if I have indemnity insurance?

You can, but contacting the council can end the policy’s cover. Check the policy wording and speak to your solicitor first.

Does regularisation cover planning permission?

No. Building regulations and planning are separate. If the work also needed planning permission, that is a separate retrospective planning application. A lawful development certificate may help if the work was permitted development.

Get a Free Quote for Your Project

Send us what was built, roughly when, and any photos, drawings or invoices you have. We will tell you what the council is likely to need and give you a free quote for the drawings, calculations and reports.

Last reviewed: November 2026. Checked against regulation 18 of the Building Regulations 2010 and section 36 of the Building Act 1984 on legislation.gov.uk (both up to date to 18 November 2026). Council charges and processes vary. General guidance for England only. Get project-specific advice before relying on it.