Building Control Completion Certificates

A completion certificate is the document that says finished building work has been checked and meets the Building Regulations. The council gives one at the end of a job. A private approver gives a final certificate, which does the same job. Buyers’ solicitors and lenders usually ask to see it, so it is worth getting it on time and keeping it safe. This guide covers England.

Free quotesSend your drawings for a price
6-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm
Developer guide

What a completion certificate is

There are four kinds of certificate, depending on who checked the work.

01

Completion certificate

Given by the council when it is satisfied the finished work complies. For a higher-risk building it comes from the Building Safety Regulator instead.

02

Final certificate

Given by a private Registered Building Control Approver to the council when the work complies. It is the private version of a completion certificate.

03

Regularisation certificate

Given by the council for work that was done without building control approval. Only the council can give one, and only for work carried out after 11 November 1985.

04

Competent person certificate

Given by an installer registered with a scheme, for work such as windows, boilers and electrics. GOV.UK says you should get it within 8 weeks of the work being finished.

The law says each of these certificates is evidence, but not conclusive evidence, that the work meets the rules it covers.

How it works

How to get your completion certificate

01

Book the final inspection

Tell your building control body when the work is finished, so it can carry out its last visit before anything is handed over.

02

Send the completion notice within 5 days

The person carrying out the work must give the building control body a notice no more than 5 days after the work is finished.

03

Include the signed statements

The notice must include a statement signed by the client that, as far as they know, the work complies, and statements from the principal contractor and principal designer that they carried out their duties. If one of them cannot be included, the notice must say why.

04

Send the reports and test results

The council checks the energy and carbon targets, water efficiency, fire safety information and the energy performance certificate as well as the building work itself. For a new home that usually means the as-built SAP calculation, the EPC, the water calculation and the air test results.

05

Put right anything the inspector raises

The certificate is only given once the building control body is satisfied the work complies.

How it works

Council or private approver: how the certificate differs

Council Private approver
What you get Completion certificate Final certificate
Who gives it The council’s building control team The approver, to the council. Ask the approver for your own copy
Time limit 8 weeks from the day the council receives the completion notice Given when the approver is satisfied. The council then has 10 working days to reject it
Work already done without approval Regularisation certificate Not available

Since 6 November 2026, the council’s 10 working days run from the day the final certificate is given or the day its charge for the certificate is paid, whichever is later.

Developer guide

New homes and the Building Safety Levy

From 1 October 2026, the Building Safety Levy is charged on many new homes in England. Where levy information had to be sent with a full plans application, the completion notice must also include a levy liability statement. The council cannot give the completion certificate until the levy collecting authority confirms it agrees with that statement.

Leave time for this at the end of the job, especially if buyers are waiting to complete. Our Building Safety Levy calculator gives an idea of the amount.

Want the end of the job sorted?

We help collate test certificates, commissioning records, photographs, declarations and other completion information, and we can arrange the as-built SAP, air test, water calculation and EPC.

Developer guide

What happens if you do not get one

01

Selling becomes harder

GOV.UK warns that without approval you will not have the certificates you may need when you sell your home.

02

The council can act

It can require work that breaks the Building Regulations to be taken down or altered for up to 10 years after it was finished, for work finished on or after 25 April 2024. It used to be 12 months.

03

Fines are possible

The person doing the work can be prosecuted and fined for not following the Building Regulations.

If the council refuses to give a completion certificate or a regularisation certificate, you can appeal to the Building Safety Regulator. Appeals have time limits, so start as soon as you get the decision. The steps are on GOV.UK.

Developer guide

Lost your completion certificate?

01

Ask the council first

Its building control team keeps records of applications and certificates. A private approver’s final certificate is given to the council, so the council should hold it too. Some councils charge for a copy.

02

Ask the approver

If a private approver checked the work, ask it for a copy of its final certificate.

03

Check the installer’s scheme

For windows, boilers or electrics, search the Competent Persons Register for the installer and ask their scheme for a copy.

04

No certificate was ever given

The council may be able to give a regularisation certificate. You may have to open up or alter some of the work first.

If you are selling, talk to your solicitor before you contact the council, so they can tell you which option suits the sale.

Your questions

Frequently asked questions

How do I find a Building Control completion certificate?

Ask the council’s building control team, which keeps records of applications and certificates, including final certificates from private approvers. Some councils charge for a copy. If a private approver checked the work, you can also ask them.

Do I need a Building Control completion certificate?

If the work needed building control approval, you should get a completion or final certificate at the end. It is evidence that the work meets the Building Regulations, and buyers’ solicitors and lenders usually ask for it. Our guide Do I need Building Control approval? explains which work needs it.

Can I sell my house without a Building Control certificate?

You can, but the buyer’s solicitor is likely to ask for it, and GOV.UK warns that without approval you will not have the certificates you may need when selling. Ask the council for a copy first. If none was ever given, talk to your solicitor about the options, which can include a regularisation application.

What happens if I don’t get a completion certificate?

You may struggle to sell or remortgage, and the council can still require work that breaks the rules to be taken down or altered. For work finished on or after 25 April 2024 it has up to 10 years to do so.

How long does a completion certificate take?

The council has 8 weeks from the day it receives the completion notice, as long as the work complies. A private approver gives its final certificate when it is satisfied, and the council then has 10 working days to reject it.

Is a final certificate the same as a completion certificate?

It does the same job. A final certificate comes from a private Registered Building Control Approver and a completion certificate comes from the council. Both are evidence that the work meets the Building Regulations.

Who sends the completion notice?

The person carrying out the work, usually the builder or main contractor, no more than 5 days after the work is finished. It includes signed statements from the client, the principal contractor and the principal designer.

Get a Free Quote for Your Project

We help collate test certificates, commissioning records, photographs, declarations and other completion information, and we can arrange the as-built SAP, air test, water calculation and EPC.

Last reviewed: November 2026. Based on the Building Regulations 2010 (regulations 16 and 17), the Building (Registered Building Control Approvers etc.) (England) Regulations 2024 (regulations 13 and 22A) and GOV.UK guidance, for England. Your building control body has the final say.