Gateway 2: How to Apply
Before building work starts on a new higher-risk building in England, you need building control approval from the Building Safety Regulator. This is known as Gateway 2. Work cannot start until the application is approved, so a complete, well-prepared application is the best way to protect your programme. This guide explains what goes in it and what happens next.
In this guide
Which buildings are higher-risk?
During design and construction, a higher-risk building is one that meets both of these tests:
Height
At least 18 metres high, or at least 7 storeys.
Use
At least 2 homes, or a hospital or a care home.
Gateway 2 also covers certain work to existing higher-risk buildings, and work that turns a building into one.
The three gateways
Gateway 1, planning
A fire statement goes in with the planning application for buildings of 18 metres or 7 storeys and over with 2 or more homes.
Gateway 2, before work starts
The Building Safety Regulator must approve the building control application before any building work begins.
Gateway 3, at completion
You apply for a completion certificate. Residents cannot move in until it is issued and the building is registered with the Building Safety Regulator.
Who applies?
The client is responsible for the application and for making sure its information is correct. The client can authorise someone else, such as a consultant, to make the application and manage it, but needs to give that authority in writing and stays legally responsible. The application names the client, the principal designer and the principal contractor, so they need to be appointed first.
For higher-risk buildings, the Building Safety Regulator is the building control authority. A council or a private building control approver cannot approve this work. Since January 2026 the regulator has been a standalone public body.
What goes in a Gateway 2 application?
The application has to show how the building will meet the building regulations, not just state that it will. For a new higher-risk building, it includes:
The work and the drawings
A description of the work, the building’s height, storeys and use, a site location plan and the drawings that show how it complies.
Compliance statement
How the work will meet the building regulations, the standards you will follow and why.
Fire and emergency file
The fire strategy, with plans covering escape, fire spread, fire service access and how the building will be managed.
Construction control plan
How compliance will be managed and checked on site, and how evidence will be collected.
Change control plan
How changes during the build will be recorded, assessed and approved.
Occurrence reporting plan
How the principal designer and principal contractor will report serious fire and structural safety issues.
Competence declaration
Signed by the client, confirming the checks made on the principal designer and principal contractor.
Partial completion strategy
Only if part of the building will be lived in before the rest is finished.
A construction phase health and safety plan is not a construction control plan. Sending one in its place can get the application rejected.
How long does Gateway 2 take?
| Type of application | Time the regulator takes |
|---|---|
| New higher-risk building | Up to 12 weeks |
| Work to an existing higher-risk building | Up to 8 weeks |
These periods can be extended by agreement, and the time taken depends on the quality of the application and how complex the work is. The regulator charges for assessing applications under its charging scheme.
What happens after approval?
Before you start
Tell the regulator at least 5 working days before work starts, and again within 5 working days of the work reaching commencement.
Building to the approved plans
The approved documents become the agreed plans. Any change to them must go through your change control plan and be recorded in a change log.
Bigger changes
Some changes must be reported to the regulator. For a major change, work on that part must stop until the regulator approves it.
Completion
When the work is finished, you apply for a completion certificate. This is Gateway 3.
How we can help
Gateway applications are one of our services. A Gateway 2 application draws on reports that many projects need anyway, such as the fire strategy and structural design, and we can arrange these with one project manager for the job. Send us your drawings and we will set out what your application needs.
Frequently asked questions
Can I start work before Gateway 2 is approved?
No. You must not start any building work on a new higher-risk building until the Building Safety Regulator has approved the building control application.
Does my building need a Gateway 2 application?
It does if the building is at least 18 metres high or has at least 7 storeys, and has at least 2 homes or is a hospital or care home. Certain work to an existing higher-risk building needs approval too.
How long does Gateway 2 take?
Up to 12 weeks for a new higher-risk building and up to 8 weeks for work to an existing one, unless a longer period is agreed. A complete, clear application helps avoid delays.
Can a Private Building Control approver handle a higher-risk building?
No. The Building Safety Regulator is the building control authority for higher-risk buildings in England.
Who submits the Gateway 2 application?
The client is responsible. They can authorise someone else in writing to make the application for them, but stay legally responsible for it.
What happens if the design changes after approval?
Changes go through the change control plan and are recorded. Some must be reported to the regulator, and for a major change, work on that part stops until the regulator approves it.
Get a Free Quote for Your Project
Send us your drawings and project details. We will look at what your Gateway 2 application needs and arrange a free quote.
Last reviewed: November 2026. General guidance for England only, based on GOV.UK guidance from the Building Safety Regulator. Get project-specific advice before relying on it.