SuDS Drainage Strategy for Planning
If the council or the Lead Local Flood Authority has asked for a drainage strategy, a SuDS strategy or a surface water drainage plan, this guide explains what they want. A strategy shows where the rain falling on your new roofs and hard surfaces will go, how much needs holding back, and how the design meets the national SuDS standards.
In this guide
When do you need a drainage strategy?
Most requests come in one of three ways:
With the application
Many councils list a surface water drainage strategy on their checklist for major applications, so the application may not be registered without one. Major means 10 or more homes, or a site of half a hectare or more where the number of homes is not yet known.
From the flood authority
On major schemes the council must consult the Lead Local Flood Authority on surface water drainage. If it raises concerns, the application can stall until a strategy is sent.
As a planning condition
Many permissions say no work can start until a surface water drainage scheme has been approved. See our guide to discharging planning conditions.
Smaller sites are asked too, especially where there is a history of flooding, a surface water flood risk, or no public surface water sewer nearby.
Where the rainwater should go
The first national standard sets an order of places for the water to go. You use the first one that is practical, and only move down the list when you can show why the one above will not work. Higher cost on its own is not accepted as a reason, and rainwater must never go into a foul sewer.
- Collected and reused, for example in water butts or rainwater harvesting.
- Soaked into the ground.
- Into a ditch, stream, pond or other surface water body.
- Into a surface water sewer.
- Into a combined sewer, as a last resort.
The national SuDS standards in plain words
The government’s national standards for sustainable drainage apply in England. They are guidance, but councils and flood authorities use them to judge planning applications, so your strategy needs to show how it meets each one. There are seven, covering these areas:
Where the water goes
Follow the order above.
Everyday rain
Aim to stop at least the first 5 mm of most rainfall running off the site, using things like green roofs, permeable paving, rain gardens and swales.
Heavy rain and flooding
The system is designed for a 1 in 30 and a 1 in 100 year storm, with an allowance for climate change. Water leaving the site is held to the greenfield rate or 3 litres a second per hectare, whichever is higher.
Water quality
Runoff is cleaned before it leaves the site.
Amenity and wildlife
Drainage should make the place better to live in where it can. Ponds, swales and planting can also support wildlife and help with Biodiversity Net Gain.
Building and upkeep
Every scheme needs a management and maintenance plan saying who looks after it and how.
What goes in a drainage strategy?
The exact content depends on the site and what the council has asked for. A typical strategy covers:
- The site, the proposed layout and the council’s or flood authority’s request.
- Where the water can go, worked down the order above, with the reasons.
- Greenfield runoff rates and how much water needs storing on site.
- How the design meets each of the seven standards.
- A drawing showing the main drainage runs and features.
- Who will look after the system, and how.
Soakaways and ground conditions
Soaking water into the ground is high on the list, so the flood authority will want to know whether your ground can take it. That needs a soakaway percolation test. On some sites a ground investigation is needed too, for example where there is clay, filled ground or contamination. We can arrange both, so the strategy is based on real test results rather than guesses.
Flood risk assessment or drainage strategy?
They are different reports, and some sites need both.
Flood risk assessment
Looks at whether the site itself could flood, from rivers, the sea, surface water or groundwater. See flood risk assessments.
Drainage strategy
Deals with the rain that falls on your new roofs and hard surfaces, and makes sure the development does not add to flooding elsewhere.
Sites in Flood Zone 2 or 3, or of one hectare or more, usually need a flood risk assessment as well. It makes sense to ask for both together, because they use the same drawings.
Frequently asked questions
Do I need a drainage strategy for planning?
Usually for major applications (10 or more homes, or half a hectare or more), and often for smaller sites where the council has flooding concerns. Check the council’s validation checklist or the wording of your planning condition. If you are not sure, send us the request and we will tell you.
What is SuDS?
SuDS stands for sustainable drainage systems. Instead of piping all rainwater straight into a sewer, SuDS slows it down, stores it and lets it soak away where it can, using things like permeable paving, swales, ponds, green roofs and underground storage crates.
Are the national SuDS standards law?
They are government guidance for England. Councils and flood authorities use them to judge planning applications, so your strategy needs to show how it meets them.
Can I just connect to the public sewer?
Only if the options higher up the list, such as reuse, soakaways or a nearby watercourse, are not practical. You need to show why each one will not work, and higher cost alone is not accepted. You will also need the water company’s agreement to connect.
Do I need a percolation test first?
If you want to use soakaways, or permeable paving that drains into the ground, yes. The flood authority will expect test results, and without them a strategy can be held up.
Who looks after the SuDS once the site is built?
The strategy includes a management and maintenance plan that says who is responsible. On a single house that is usually the owner. On a larger site it may be a management company, the water company or the council.
Get a Free Quote for Your Project
Send us your site plan, the proposed layout and the council’s request, and we will come back with a free quote.