Renovating Thermal Elements

Renovating a thermal element means re-doing part of an outside wall, roof or floor of a heated building, for example re-roofing, re-rendering or dry-lining a wall. If you renovate more than half of that wall, roof or floor, the Building Regulations say the whole of it must be insulated to a set standard, as far as that is practical and pays for itself. This guide explains what counts, the 50% rule, the U-values to reach and when to tell Building Control.

Free quotesSend your drawings for a price
9-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm

The points below come from regulations 2, 3 and 23 of the Building Regulations 2010 and Approved Document L Volume 1 (homes). They apply in England. Other buildings, such as shops and offices, follow Approved Document L Volume 2, which works in the same way but has its own tables.

The basics

What is a thermal element?

Regulation 2(3) defines a thermal element as a wall, floor or roof that separates the heated part of a building from the outside, from the ground, or from an unheated part of the building. Windows, doors, roof windows and rooflights are not thermal elements; they have their own rules.

01

Walls

External walls, and walls between a heated room and an unheated garage, store or loft space.

02

Roofs

Pitched and flat roofs over heated rooms, including the roof and side walls (cheeks) of dormers.

03

Floors

Ground floors, and floors over an unheated space such as an integral garage or a passageway.

Developer guide

What counts as renovating a thermal element?

Paragraph 11.2 of Approved Document L lists five kinds of work. Painting, patch repairs and like-for-like small repairs are not on the list.

01

A new layer outside

Cladding or rendering the outside face of a wall.

02

A new layer inside

Dry-lining the inside face of an outside wall.

03

Stripping back and rebuilding

Taking a wall, roof or floor back to its bricks, blocks, rafters, joists or frame and building it up again, for example stripping a roof down to the rafters or hacking off old plaster back to the brickwork.

04

A new flat roof covering

Replacing the waterproof membrane on a flat roof.

05

Cavity wall insulation

Filling an existing cavity.

Developer guide

The 50% rule and major renovations

Regulation 23(1) says that if you renovate more than 50% of the surface of an individual thermal element, or the work is a major renovation, the whole of that element must be brought up to the energy standard in Part L, in so far as that is technically, functionally and economically feasible.

01

Working from outside

If you take render off the outside of a wall, the element is the whole elevation that wall sits in. Re-render more than half of that elevation and the whole elevation should be insulated.

02

Working from inside

If you take plaster off the inside of a wall, the element is the area of outside wall as seen from inside that room. Re-plaster more than half of it and the whole of that wall in that room should be insulated.

03

Major renovation

When more than 25% of the surface area of the whole outside envelope of the building is renovated, the work is a major renovation and the 50% test no longer matters for those elements.

04

Replacing, not renovating

Regulation 23(2) uses the same 50% test where you replace an element outright, for example demolishing and rebuilding a wall. Replacement elements have to meet the tighter new-element standards in Table 4.2, such as 0.18 for a wall and 0.15 for a roof.

Developer guide

The U-values to aim for

A U-value measures how much heat escapes through a wall, roof or floor. The lower the number, the better the insulation. Table 4.3 of Approved Document L sets two figures for existing elements in existing homes. A renovated element should reach column (b), and should never end up worse than it was before.

Element Threshold (a) Improved standard (b)
Roof 0.35 0.16
Wall, cavity insulation 0.70 0.55
Wall, internal or external insulation 0.70 0.30
Floor 0.70 0.25

All figures are in W/m²K, averaged over the element. The threshold in column (a) is used when existing walls, roofs and floors are kept in a conversion, such as a loft, garage or barn: anything worse than the threshold should be upgraded to column (b). The 2026 edition of Approved Document L, which takes effect on 24 March 2027, keeps the same figures in its Table 3.3.

Do you need one?

When the full standard is not practical

The rules do not force work that cannot be done or will never pay back. Paragraph 4.13 says that if reaching column (b) is not technically or functionally feasible, or would not pay for itself within 15 years, the element should be upgraded to the best U-value that is feasible and does pay back within 15 years.

01

The 15-year payback

Simple payback is the extra cost of the insulation divided by the yearly saving on energy bills, using energy prices current when the application is made.

02

The 0.7 backstop

Generally an upgraded element should not be left with a U-value worse than 0.70, unless a lesser standard is needed to avoid condensation under Part C.

03

Room size

If insulating a wall would cut the floor area of the room by more than 5%, a lesser standard may be accepted.

04

Headroom and floor levels

A lesser standard may also be accepted where roof insulation would limit headroom, where a flat roof frame or upstand cannot take it, or where floor insulation would cause real problems with adjoining floor levels.

05

Older and listed buildings

Listed buildings, homes in conservation areas and scheduled monuments need not comply fully where it would unacceptably alter their character. Older solid stone, cob or lime-built walls should only be insulated if it will not cause long-term damage from trapped moisture. Building control should take the conservation officer’s advice.

Developer guide

Common jobs and their targets

Appendix C of Approved Document L gives target U-values that count as a reasonable improvement in ordinary cases. They are a starting point; the payback and practical limits above still apply.

Work U-value Typical way to reach it
Re-roofing a pitched roof with a cold loft 0.16 About 250 mm of mineral or cellulose fibre in the loft, between and over the ceiling joists
Re-roofing with rooms in the roof 0.16 Insulation between and below, or between and above, the rafters
Replacing a flat roof covering 0.16 Insulation between and over the joists
Dormer cheeks re-clad 0.30 Insulation between or outside the studs
Re-plastering a solid outside wall 0.30 Insulated dry-lining or insulated plasterboard
Re-rendering or re-cladding a wall 0.30 External wall insulation with render or cladding
Replacing a floor screed or timber deck 0.25 Insulated deck, or insulation between the joists

Where insulation is returned along party walls and sound matters, the guidance says a wall target of 0.35 or above may be more appropriate. Condensation risk should be checked on every job, and for older buildings BRE report BR 262 and Historic England’s guidance are named as the references.

Do you need one?

Do you need to tell Building Control?

Yes, in most cases. Regulation 3(1)(h) makes work required by regulation 23 “building work”, and regulation 3(1)(e) does the same for filling a cavity wall. So the work needs either a Building Control application or an installer who can self-certify it.

01

Self-certification

Schedule 3 of the Building Regulations lets registered installers sign off their own work: replacement roof coverings (NAPIT or the National Federation of Roofing Contractors), cavity wall insulation, and internal or external wall insulation (schemes such as Certsure, NAPIT, CERTASS and Blue Flame). They tell the council for you.

02

Building Control application

If your builder is not registered for that type of work, apply to Building Control before starting. A building notice is often enough for a house; a full plans application suits bigger or more complex jobs.

03

Other parts of the regulations

Approved Document L says to pay particular attention to Part B (fire), Part C (damp and condensation), Part F (ventilation) and Part J (fuel-burning appliances), as extra insulation can change how a building handles moisture, air and flues.

04

Planning is separate

External wall insulation and new roof coverings can change how a building looks. Check whether planning permission or listed building consent is needed as well.

Renovating, converting or extending?

Send us the drawings and a note of the work. We can work out the U-values the wall, roof or floor needs, provide the SAP calculations for a conversion or extension, and handle Building Control, with one project manager for the lot.

Your questions

Frequently asked questions

What are the building regulations for renovating a thermal element?

Regulation 23 of the Building Regulations 2010. If you renovate more than 50% of an outside wall, roof or floor, or more than 25% of the whole building envelope, the whole element must be insulated to the Part L standard where that is technically, functionally and economically feasible. For homes the target is in Table 4.3 of Approved Document L: 0.16 for roofs, 0.30 for walls insulated inside or out, 0.55 for cavity fill and 0.25 for floors.

Do I need building regulations to replace my roof?

Replacing a roof covering is renovating a thermal element, so the roof should be insulated to about 0.16 where that is practical. A roofer registered with NAPIT or the National Federation of Roofing Contractors can self-certify the work. Otherwise apply to Building Control before you start. Small repairs, such as replacing a few slates, are not covered.

Does re-plastering a wall need building regulations?

It can. Hacking off plaster back to the brickwork on an outside wall is renovating a thermal element. If you re-plaster more than half of that wall, as seen from inside the room, the whole wall should be insulated to 0.30 where that is practical, for example with insulated plasterboard. A lesser standard is accepted if the room would lose more than 5% of its floor area.

What is the 50% rule in Part L?

If more than 50% of the surface of an individual wall, roof or floor is renovated or replaced, the whole of that element has to meet the energy standard, not just the part you worked on. From outside the element is the whole elevation; from inside it is the outside wall of that room.

What is a major renovation under the Building Regulations?

A major renovation is when more than 25% of the surface area of the building’s whole outside envelope (walls, roof and floor together) is renovated. The elements being renovated then have to meet the Part L standard as far as is feasible, whatever share of each one is done.

Do building regulations apply to refurbishments?

Some refurbishment work is building work. Renovating a thermal element, filling a cavity wall, structural alterations, new drainage, electrics in some cases, and replacing windows or boilers all fall under the Building Regulations. Redecorating, new kitchens without structural or service changes and small repairs usually do not.

What if the insulation will not pay for itself?

The element should then be upgraded to the best U-value that does pay back within 15 years and is practical to build. In general it should still not be left worse than 0.70, unless a lesser standard is needed to avoid condensation. Building Control may ask to see the payback sums.

Do listed and older buildings have to meet these U-values?

Not fully where it would unacceptably alter the character or appearance of a listed building, a home in a conservation area or a scheduled monument. Older stone, cob or lime-built walls should only be insulated if it will not trap moisture and damage the fabric. The work should still improve energy efficiency as far as is reasonably practicable, and Building Control should take the conservation officer’s advice.

Get a Free Quote for Your Project

Send us the drawings and a note of the work. We can work out the U-values the wall, roof or floor needs, provide the SAP calculations for a conversion or extension, and handle Building Control, with one project manager for the lot.

Last reviewed: November 2026. Checked against regulations 2(3), 3(1) and 23 and Schedule 3 of the Building Regulations 2010 (legislation.gov.uk), and Approved Document L Volume 1, 2021 edition incorporating 2023 amendments, paragraphs 0.8 to 0.13, 4.11 to 4.13, 11.2 to 11.4, Tables 4.2 and 4.3 and Appendix C, and the 2026 edition (Table 3.3) taking effect on 24 March 2027. General guidance for homes in England only. Get project-specific advice before relying on it.