Part S Building Regulations: EV Charging Points Explained

Since June 2022, most new homes in England with a parking space have needed an electric vehicle charge point to pass Building Control. Part S of the building regulations sets out when you need one, how many, and when cable routes are enough. This guide explains the rules in plain English and what the government’s new consultation could change.

Free quotesSend your drawings for a price
8-minute readPlain-English guide for developers
Reviewed November 2026Guidance for England
02475 095700Mon to Fri, 9am to 5pm
Developer guide

Quick answers

01

New house with its own parking space

One charge point per house.

02

Block of flats with outdoor parking

One charge point for each flat that has a parking space. Spaces in a covered car park only need cable routes today.

03

Building converted into homes, with parking

One charge point per new home with a parking space, where the work includes the car park or its electrics and the existing supply can take it.

04

Major renovation of homes with more than 10 parking spaces

A charge point for each home with parking, plus cable routes to every other space.

05

New or majorly renovated commercial building with more than 10 parking spaces

One charge point, plus cable routes to at least one fifth of the remaining spaces.

06

Charge point standard

At least 7kW, with a universal socket rather than a fixed cable, and a smart charger that meets the 2021 smart charge point rules.

Developer guide

Who does Part S apply to?

Part S applies in England to:

  • new homes with an associated parking space (a space within the site boundary for the people living there or their visitors)
  • buildings changing use into homes, where there is parking and the work includes the car park or its electrical supply
  • residential buildings having a major renovation, where there will be more than 10 parking spaces
  • new non-residential buildings with more than 10 parking spaces
  • non-residential buildings having a major renovation, where there will be more than 10 parking spaces
  • mixed-use buildings with parking, which have their own rules for the homes and the rest of the building

A “major renovation” means work on more than 25% of the surface area of the building’s outer envelope.

Part S applies in England only. Wales, Scotland and Northern Ireland set their own building rules.

Developer guide

Part S at a glance: requirements S1 to S6

Part S is the part of the Building Regulations 2010 that covers infrastructure for charging electric vehicles. It has six requirements, one for each kind of project. Approved Document S is the government’s guidance on how to meet them.

Requirement What it covers
S1 New residential buildings
S2 Homes created by a material change of use
S3 Residential buildings having a major renovation
S4 New buildings that are not residential or mixed-use
S5 Major renovation of buildings that are not residential or mixed-use
S6 New mixed-use buildings, and mixed-use buildings having a major renovation

The minimum standard for the charge point itself is set separately, in regulation 44J of the Building Regulations.

Do you need one?

When did Part S start?

Part S came into force on 15 June 2022. It does not apply where a building notice, an initial notice or full plans went in before that date and the work started before 15 June 2023. Every project applied for since then has to meet it.

Do you need one?

How many charge points do I need?

Type of project Charge points Cable routes
New home with parking 1 per home with a parking space Only where the cost cap or a covered car park means a charge point isn’t required
Change of use into homes, with parking 1 per new home with a parking space, within the existing supply To the remaining spaces if the supply can’t take them all
Residential major renovation, more than 10 spaces 1 per home with a parking space To every other space
New commercial building, more than 10 spaces 1 To at least one fifth of the remaining spaces
Commercial major renovation, more than 10 spaces 1 To at least one fifth of the remaining spaces

A cable route is a safe route from the power supply to the planned charge point, so cabling can be added later without digging up the car park.

Prices

The £3,600 cost cap and other exemptions

You don’t always have to fit every charge point. The main exceptions are:

01

Grid connection cost cap (new homes)

You fit as many charge points as you can at an average connection cost of £3,600 per charge point or less, and cable routes to the rest. On a site with several new homes the cost can be averaged.

02

Existing supply (change of use and major renovations)

Charge points are only needed as far as the building’s existing electrical supply allows. Cable routes go to the remaining spaces.

03

7% rule (major renovations)

If charge points and cable routes would cost more than 7% of the total renovation cost, you only need cable routes. If cable routes alone would cost more than 7%, you need neither.

04

Covered car parks

Spaces under a roof only need cable routes today. Carports and residential garages don’t count as covered car parks. This is one of the things the consultation wants to change.

05

Listed buildings and conservation areas (change of use)

Exempt where the work would unacceptably alter their character or appearance.

06

Fire safety works (residential major renovations)

Exempt where the main purpose is to improve the fire safety of the external walls or roof.

To rely on the cost cap, give Building Control at least two formal quotes at the plans or notice stage. At least one must come from the distribution network operator.

Need EV charging signed off on your development?

Send us your site plan and the number of homes and parking spaces. We will review what you need and price the supply and installation.

Developer guide

What the 2026 consultation could change

On 21 October 2026 the government opened a consultation on Part S. It closes at 11:59pm on 16 December 2026. Nothing has changed yet, and there is no start date for any new rules. The main proposals are:

  1. Covered car parks: new and majorly renovated enclosed and open-sided car parks would need charge points, not just cable routes.
  2. The £3,600 cap: the government is asking whether the cap is at the right level given inflation since 2021, and whether to raise it each year in line with CPI.
  3. Better charge points: minimum standards for load management and PEN fault protection, plus changes on wiring standards and voltage drop.
  4. Clearer words: plainer definitions of “major renovation” and “cable route”.
  5. Tethered chargers: possibly more freedom to fit chargers with a fixed cable.
  6. Fire safety: views on the 2023 interim guidance for electric vehicles in covered car parks.

A separate consultation looks at making it easier for tenants and leaseholders to get EV charging.

What this means for you: if you are designing flats with under-croft or basement parking, or a site where the grid connection is expensive, allow for the rules tightening.

Will other building regulations change too? In the October 2026 Budget the government said it will not make major changes to building regulations for the rest of this Parliament, except to keep improving building safety. The Future Homes Standard still starts on 24 March 2027. See our Future Homes Standard 2027 guide.

How it works

How Part S is signed off

  1. Design stage: show the charge points and cable routes on your site plan and electrical drawings.
  2. Building Control application: your Building Control body checks the numbers against Part S.
  3. Grid connection: if you are relying on the £3,600 cap, get the quotes early.
  4. Installation: a qualified installer fits and tests the charge points.
  5. Completion: give Building Control the evidence it asks for before the completion certificate.
How it works

How One Stop Consult can help

Your questions

Frequently asked questions

Do all new builds need an EV charger?

In England, every new home with an associated parking space needs a charge point, unless the cost cap applies or the space is in a covered car park. Homes without a parking space don’t.

Do I need an EV charger for a house extension?

No. Part S applies to new homes, change of use into homes and major renovations, not to extensions.

Do flat conversions need EV charging points?

They can. Each new flat with a parking space needs one where the work includes the car park or its electrics and the existing supply can take it. Otherwise cable routes may be needed instead.

What is the £3,600 cap?

For new homes, you fit as many charge points as you can at an average connection cost of £3,600 each or less, and cable routes to the other spaces. The government is consulting on this figure.

What power does the charger need to be?

At least 7kW, and it must be a smart charger that meets the Electric Vehicles (Smart Charge Points) Regulations 2021.

When will the new Part S rules start?

There is no date yet. The consultation closes on 16 December 2026, and the government will publish its response after that.

What is Approved Document S?

Approved Document S is the government’s guidance on meeting Part S of the Building Regulations in England, which covers infrastructure for charging electric vehicles. It was first published in December 2021 and covers requirements S1 to S6.

When did Part S come into force?

On 15 June 2022. Projects with a building notice, initial notice or full plans in before that date were exempt, as long as work started before 15 June 2023.

Who checks Part S?

Your Building Control body, council or private, checks Part S as part of your application.

Get a Free Quote for Your Project

Send us your site plan and the number of homes and parking spaces. We will review what you need and price the supply and installation.

Last reviewed: November 2026. General guidance for England only. Building Control has the final say on any project, so get project-specific advice before relying on it.