The story of the job
Nine detached homes on land next to Station Road in Bagworth: six two-bedroom bungalows, one three-bedroom house and two four-bedroom houses.
We brought in our supply chain partners for Building Control and the 10 Year Structural Warranty. We also coordinated the SAP calculations, air tightness, sound insulation and ventilation testing, Energy Performance Certificates and water efficiency calculations.
Foundations started in January 2023 to the structural engineer's design, at depths of 1.5m to 2.1m below finished floor level with two layers of B385 mesh. Waterlogged ground slowed the block and beam floors that month. Further plots followed in April and May 2023 at around 1.0m deep in sand and gravel with clay content.
Brickwork and roof trusses followed through 2023, with breathable felt and tile battens going on by October. Roof tiling with a mechanically fixed ventilated ridge was in place by May 2024. By September 2024 drain tests had been witnessed and all internal and external works were complete.